Email:
[email protected], [email protected], [email protected]
KEYWORDS cost, duration, CPM, schedule, construction |
ABSTRACT This study aims to obtain
the form of project work network in the Probolinggo
City Hospital Development Project, to determine the effect of accelerating
the duration of Probolinggo City Hospital
Development work on network planning and to find out the amount of costs
incurred before and after the acceleration of the duration of project work.
The method used is the acceleration method with modification of the
scheduling of the CPM model. CPM method planning is a recommendation in choosing
from many existing methods, because there is a calculation of the earliest
time the project starts, the last time the project starts as well as the
earliest time to finish and the last time to finish so that it can be known
the time lag of all activities. Data Used are primary and secondary data
related to the sequence and relationship of activities, implementation time
and cost budget plan (RAB). In this thesis, the author takes scheduling data
from the Probolinggo City Hospital Development
Project which will be used as the basis for writing this thesis in conducting
CPM analysis and accelerating the duration of work with additional overtime
working hours and calculating the total cost of the acceleration to be used
as comparison material in the writing results. Based on the analysis that has
been carried out using the Microsoft Project 2016 application, the normal
duration of structural work is 81 working days and has 18 critical units of
31 work items. After the acceleration was carried out, there was a decrease
in the duration of the work of the structure to 74 working days. The
difference in duration decrease was 7 days or 9.45%. The total initial cost
with the normal duration for structural work is IDR 28,563,131,560, while
after acceleration, the project cost for structural work becomes IDR
28,635,083,793 |
INTRODUCTION
Project
scheduling is an activity that sets the timeframe of project activities to be
completed, raw materials, labor and time required by each activity. Scheduling
is necessary so that project implementation can continue to take place
according to the schedule plan that has been made. However, often project
scheduling experiences problems, one of which is the occurrence of delays.� Scheduling delays can adversely affect
quality, time and cost. The construction of the Probolinggo
City Hospital was delayed so that there was a minus deviation in progress due
to the difference in the time of work implementation between the contractor's
offer and those in the contract, resulting in disruption to the start of work
implementation and due to the cash flow of underprivileged contractors. It is
feared that the retreat of the implementation schedule may interfere with the
implementation of the project, therefore it is necessary to accelerate the
duration by using the Critical Path Method (CPM) to analyze the acceleration of
the duration and its impact on costs.
It is hoped that the
results of this research can add insight for students, especially academics,
about the analysis of a project using the CPM Method.
It is expected to provide
information or recommendations to the relevant institutions (further research)
regarding critical pathways and ways to accelerate project implementation,
especially in structural work.
It is expected to provide
information or recommendations to the owner, implementing contractor and MK consultants
regarding critical paths and ways to accelerate project implementation,
especially in structural work.
Table 1 Previous Research
No |
Researchers |
Heading |
Method |
Variable |
Conclusion |
1 |
Alan Duta Prayogi,
2015 |
Acceleration
of Scheduling and Time in Building Buildings With
Critical Path Method (CPM) and Program Evaluation Review Technique (PERT)
(Case Study of Mall Building Project |
Based on the anlysis carried
out that the duration of the CPM is 427 days with the probability that it can
be completed in 427 days is 81.56%.�
And for acceleration analysis using the Time Cost Trade Off method� |
Project Cost |
In
using the Critical Path Method (CPM) and Project Evaluation Review Technique
(PERT) methods in the Dinoyo Mall building building, it is to detail the plan and sequence of
activities, work, calculate normal time (m), determine optimistic time (a),
and pessimistic time (b) on each job, and use the Microsoft Project 2007
application with input |
According to Husen (2009),
a project is a combination of resources such as material people, equipment, and
capital / costs that are collected in a temporary organizational forum to
achieve goals and objectives.
A project
is an effort carried out in a responsible way to produce a product, service
that produces a certain result (Lewis, 2005).
Defined
as a systematic effort to determine standards that are in accordance with the
goals and objectives of planning, designing information systems, comparing
implementation with standards, analyzing possible deviations, then carrying out
the necessary corrective actions so that resources can be used effectively and
efficiently in order to achieve goals and objectives (Mockler,
1972).
Project
scheduling is the activity of establishing the timeframe of project activities
to be completed, raw materials, labor as well as the time required by each
activity.
States
that network planning is a tool used to plan, schedule and control the progress
of a project. Here are some of the terms used to network the project (Gray and
Larson, 2006).
Network
Diagram is a visualization of a project based on network planning. Network
Diagram is a network that contains the trajectories of activities and sequences
of events that exist during the project organizer. Network Diagram consists of
activity symbols, event symbols and when necessary
symbols of relationships between events (dummy) (Iwawo,
2016).
Defines
CPM as a project management model that prioritizes cost as the object being
analyzed. CPM is a network analysis that seeks to optimize the total cost of a
project through a reduction in the total completion time of the project. The
use of the CPM method can save time in completing various stages of a project (Siswanto, 2007).�
Microsoft Project is software that can be used to design projects and
manage the project. The completeness of facilities and its extraordinary
ability in processing�
project data make this software the most widely used by computer
operators because its existence is able to help and facilitate users in
completing work, especially identifying�
critical work and related to project data (Setiawan, 2009).
RESEARCH METHOD
The research location is located
on Jalan Profesor Hamka, Karenglor Village, Kedupak District, Probolinggo City.
The research time is two months, starting from October to November 2022.
In this study, the Critical Path
method (CPM) method will be used. In this method, there are two kinds of estimated
time and cost for each activity. To find out the steps that will be carried out
in this study, namely (Heizer and Render, 2015):
1. Define the project and define the working fractional structure of all
structural activities contained in the project;
2. Determine which activities should be worked on first and which ones should
follow the old activities;
3. Describes a network that connects all activities or creates a network
diagram;
4. Determine the critical path to be used to assist in project scheduling
re-planning
General
Project Data
����������� The project that is the object of research is the Probolinggo
City Hospital Development Project. The location of the Probolinggo
City Hospital Development Project is located on Jalan Profesor
Hamka, Karenglor Village, Kedupak District, Probolinggo
City.
Data
Processing
Table 2 Detailed Budget Plan Cost of Structural Work Project
No |
Types of Work |
Total Price |
Activity Code |
1 |
Earthworks |
|
|
|
Soil Excavation |
IDR 111,815,277.99 |
A |
|
Sirtu's Patronage |
IDR 1.040.325.000,00 |
B |
|
Urug Sand Under Foundation and Floor t.10 cm |
IDR 65,135,945.71 |
C |
|
Working Floor Under Foundation and Floor t.10 cm |
IDR 234,605,260.58 |
D |
|
Urugan soil back excavated |
IDR 41,266,462.50 |
And |
2 |
Bottom Structure Work |
|
|
|
Stake Work |
IDR 3,101,140,000.00 |
F |
|
Pile Cap Foundation Work |
IDR 1,320,606,233.03 |
G |
|
Sloof Foundation Work |
IDR 3,178,141,803.12 |
H |
|
SFL Basic Lt. Column Work � 1,300 |
IDR 222,445,986.35 |
I |
|
Basic Lt. Plate Work |
IDR 2,483,650,565.36 |
J |
|
Ramp Jobs |
IDR 704,382,108.70 |
K |
|
Pit Lift Work |
IDR 267,750,000.00 |
L |
|
Stair Work |
IDR 151,200,000.00 |
M |
3 |
Upper Structure Work |
|
|
|
1st Floor (One) |
|
|
|
Column Work |
IDR 671,151,052.44 |
N |
|
Beam Work |
IDR 2,548,123,262.00 |
Or |
|
Plate Works Lt.1 |
IDR 1,825,621,032.15 |
P |
|
Ramp Jobs |
IDR 403,115,071.14 |
Q |
|
Stair Work |
IDR 151,200,000.00 |
R |
|
2nd (Second) Floor |
|
|
|
Column Work |
IDR 671,151,052.44 |
S |
|
Beam Work |
IDR 2,229,666,948.92 |
T |
|
Plate Works Lt.2 |
IDR 1,783,229,711.24 |
In the |
|
Ramp Jobs |
IDR 403,115,071.14 |
In |
|
Stair Work |
IDR 151,200,000.00 |
In |
|
Floor3 (Three) |
|
|
|
Column Work |
IDR 562,766,457.72 |
X |
|
Beam Work |
IDR 1,637,741,918.66 |
And |
|
Plate Works Lt.3 |
IDR 910,187,676.44 |
With |
|
Ramp Jobs |
IDR 284,670,865.28 |
AA |
|
Stair Work |
IDR 151,200,000.00 |
OFF |
|
4th (Fourth) Floor |
|
|
|
Column Work |
IDR 465,738,474.58 |
AND |
|
Beam Work |
IDR 608,877,515.50 |
TO |
|
Plate Works Lt.4 |
IDR 181,910,807.99 |
AE |
Source: Project Data
Figure 1 Gantt Chart
Source:� Research Results
Table 3 Total Slack Based on Microsoft Project 2016
Task Name |
Duration |
Start |
Finish |
Total Slack |
Predecessors |
Structural Work |
81 Days |
Wed 07/07/21 |
Sun 26/09/21 |
|
|
2.1. Earthworks |
40 Days |
Wed 07/07/21 |
Sun 15/08/21 |
|
|
A. Soil Excavation |
21 Days |
Mon 19/07/21 |
Sun 08/08/21 |
0 Days |
5 |
B. Sirtu |
12 Days |
Wed 07/07/21 |
Sun 18/07/21 |
0 Days |
|
C. Urug Sand
Under Foundation And Floor T.10cm |
21 Days |
Mon 19/07/21 |
Sun 08/08/21 |
48 Days |
4ss |
D. Foundation Bottom Work Floor And Floor T. 10 Cm |
21 Days |
Mon 19/07/21 |
Sun 08/08/21 |
0 Days |
4ss |
E. Urugan Soil
Back Excavated |
14 Days |
Mon 02/08/21 |
Sun 15/08/21 |
0 Days |
7fs-7 Days |
2.2. Lower Structure Work |
49 Days |
Mon 12/07/21 |
Sun 29/08/21 |
||
Piling Work |
21 Days |
Mon 12/07/21 |
Mon 02/08/21 |
0 Days |
8sf |
Pile Cap Foundation Work |
21 Days |
Mon 19/07/21 |
Sun 08/08/21 |
0 Days |
10ss+7 Days |
Sloof Foundation Work |
35 Days |
Mon 26/07/21 |
Sun 29/08/21 |
0 Days |
11fs-14 Days |
Lt Column Work. Sfl
Base - 1,300 |
35 Days |
Mon 26/07/21 |
Sun 29/08/21 |
65 Days |
12ss |
Basic Lt Plate Work |
35 Days |
Mon 26/07/21 |
Sun 29/08/21 |
0 Days |
12ss |
Ramp Jobs |
28 Days |
Mon 02/08/21 |
Sun 29/08/21 |
0 Days |
14ss+7 Days |
Pek Pit Lift |
35 Days |
Mon 26/07/21 |
Sun 29/08/21 |
65 Days |
14ss |
Pek Stairs |
28 Days |
Mon 02/08/21 |
Sun 29/08/21 |
0 Days |
15ss |
2.3. Upper Structure Work |
48 Days |
Mon 09/08/21 |
Tue 26/09/21 |
||
A. 1st Floor (One) |
28 Days |
Mon 09/08/21 |
Sun 05/09/21 |
|
|
Column Work |
21 Days |
Mon 09/08/21 |
Sun 29/08/21 |
0 Days |
17ss+7 Days |
Beam Work |
21 Days |
Mon 16/08/21 |
Sun 05/09/21 |
0 Days |
20fs-14 Days |
1st Plate Work |
21 Days |
Mon 16/08/21 |
Sun 05/09/21 |
0 Days |
21ss |
Ramp Jobs |
21 Days |
Mon 16/08/21 |
Sun 05/09/21 |
0 Days |
22ff |
Pek Stairs |
14 Days |
Mon 23/08/21 |
Sun 05/09/21 |
0 Days |
23fs-14 Days |
B. 2nd Floor (Two) |
35 Days |
Mon 16/08/21 |
Tue 20/09/21 |
|
|
Column Work |
21 Days |
Mon 16/08/21 |
Sun 05/09/21 |
0 Days |
24ss-7 Days |
Beam Work |
28 Days |
Mon 16/08/21 |
Sun 12/09/21 |
0 Days |
26ss |
2nd Lt Plate Work |
21 Days |
Mon 23/08/21 |
Sun 12/09/21 |
0 Days |
27ff |
Ramp Jobs |
21 Days |
Mon 30/08/21 |
Mon 20/09/21 |
0 Days |
28ss+7 Days |
Pek Stairs |
7 Days |
Mon 30/08/21 |
Sun 05/09/21 |
44 Days |
29ss |
C. 3rd (Third) Floor |
35 Days |
Mon 23/08/21 |
Sun 26/09/21 |
|
|
Column Work |
21 Days |
Mon 23/08/21 |
Sun 12/09/21 |
37 Days |
30ss-7 Days |
Beam Work |
21 Days |
Mon 23/08/21 |
Sun 12/09/21 |
37 Days |
32ss |
3rd Lt Plate Work |
21 Days |
Mon 30/08/21 |
Sun 19/09/21 |
37 Days |
33ss+7 Days |
Roof Ramp Work |
21 Days |
Mon 06/09/21 |
Sun 26/09/21 |
37 Days |
34ss+7 Days |
Pek Stairs |
7 Days |
Mon 13/09/21 |
Sun 19/09/21 |
37 Days |
35ss+7 Days |
D. 4th Floor (Four) |
21 Days |
Mon 06/09/21 |
Sun 26/09/21 |
|
|
Column Work |
14 Days |
Mon 06/09/21 |
Sun 19/09/21 |
37 Days |
36ff |
Beam Work |
14 Days |
Mon 13/09/21 |
Sun 26/09/21 |
37 Days |
38ss+7 Days |
4th Lt Plate Work |
7 Days |
Mon 20/09/21 |
Sun 26/09/21 |
37 Days |
39ss+7 Days |
Source: Research Results
������ Based on the table above, there is a
critical trajectory where the critical trajectory is the one that has a total
value of slack = 0.� The following is an
explanation of the results of the calculation of the total float above:
a. Critical Path is, a path that has total slack = 0
i.e. , B � D � E � F � G � H � J � K � M � N � O � P �
Q � R � S � T � U � V ;
b. The normal time of completion on the work of the
structure is 81 days;
After a critical trajectory is found, and the normal time of completion of
the structural work, the next step is to calculate the acceleration of the
duration of the work by adding overtime working hours.
Accelerating Project Duration
Duration of Work With Additional Overtime Working
Hours, For the calculation of the duration of accelerated time is carried out
by assuming the amount of duration according to the circumstances in the field.
This type of accelerated activity in the Probolinggo
City Hospital Development Project is work that is on a critical track.
Table 4 List
of Calculations for Adding Overtime Working Hours
Activity Name |
Normal Time |
Time Accelerated |
Time After Accelerated |
Additional Overtime (Hours) |
�Total Overtime
Fee Per Day (Rp) |
Sirtu |
12 |
4 |
8 |
4,000 |
�IDR 260,000.00 |
Working Floor Under
Foundation and Floor t.10 cm |
21 |
7 |
14 |
4 |
�IDR 377,500.00 |
Urugan soil back excavated |
14 |
4 |
10 |
3,2 |
�IDR 208,000.00 |
Stake Work |
21 |
4 |
14 |
4 |
�IDR 745,000.00 |
Pile Cap Foundation
Work |
21 |
7 |
14 |
4 |
�IDR 745,000.00 |
Sloop Foundation
Work |
35 |
12 |
23 |
4,1739 |
�IDR 576,521.74 |
Basic Lt. Plate
Work |
35 |
10 |
25 |
3,2 |
�IDR 589,000.00 |
Ramp Jobs |
28 |
10 |
25 |
3,2 |
�IDR 421,000.00 |
Stair Work |
28 |
10 |
18 |
4,4444 |
�IDR 536,111.11 |
Column Work Lt.1 |
21 |
6 |
15 |
3,2 |
�IDR 491,000.00 |
Beam Works 1st
Floor |
21 |
7 |
14 |
4 |
�IDR 613,750.00 |
Plate Works Lt.1 |
21 |
7 |
14 |
4 |
�IDR 648,750.00 |
Ramp Works 1st
Floor |
21 |
7 |
14 |
4 |
�IDR 491,250.00 |
Staircase Works 1st
Floor |
14 |
5 |
9 |
4,4444 |
�IDR 545,833.33 |
Column Work Lt.2 |
21 |
7 |
14 |
4 |
�IDR 613,750.00 |
Block Works 2nd
Floor |
28 |
10 |
18 |
4,4444 |
�IDR 681,944.44 |
Plate Works Lt.2 |
21 |
7 |
14 |
4 |
�IDR 648,750.00 |
Ramp Works 2nd
Floor |
21 |
7 |
14 |
4 |
�IDR 465,000.00 |
Source: Research Results
The next step is to calculate the cost due to the addition of overtime
working hours. In the initial planning, the duration for structural work was 81
days with details of structural costs of Rp. 28,563,131,560.06
Table 5 List
of Cost Calculations Due to Additional Overtime Working Hours
Activity Name |
Time Accelerated |
Total Overtime Fee Per Day (Rp) |
Total Cost After Expedited |
Sirtu |
4 |
�IDR 260,000.00 |
�IDR 1,040,000.00 |
Working Floor Under
Foundation and Floor t.10 cm |
7 |
�IDR 377,500.00 |
�IDR 2,642,500.00 |
Urugan soil back excavated |
4 |
�IDR 208,000.00 |
�IDR 832,000.00 |
Stake Work |
4 |
�IDR 745,000.00 |
�IDR 2,980,000.00 |
Pile Cap Foundation
Work |
7 |
�IDR 745,000.00 |
�IDR 5,215,000.00 |
Sloop Foundation
Work |
12 |
�IDR 576,521.74 |
�IDR 6,918,260.87 |
Basic Lt. Plate
Work |
10 |
�IDR 589,000.00 |
�IDR 5,890,000.00 |
Ramp Jobs |
10 |
�IDR 421,000.00 |
�IDR 4,210,000.00 |
Stair Work |
10 |
�IDR 536,111.11 |
�IDR 5,361,111.11 |
Column Work Lt.1 |
6 |
�IDR 491,000.00 |
�IDR 2,946,000.00 |
Beam Works 1st Floor |
7 |
�IDR 613,750.00 |
�IDR 4,296,250.00 |
Plate Works Lt.1 |
7 |
�IDR 648,750.00 |
�IDR 4,541,250.00 |
Ramp Works 1st
Floor |
7 |
�IDR 491,250.00 |
�IDR 3,438,750.00 |
Staircase Works 1st
Floor |
5 |
�IDR 545,833.33 |
�IDR 2,729,166.67 |
Column Work Lt.2 |
7 |
�IDR 613,750.00 |
�IDR 4,296,250.00 |
Block Works 2nd
Floor |
10 |
�IDR 681,944.44 |
�IDR 6,819,444.44 |
Plate Works Lt.2 |
7 |
�IDR 648,750.00 |
�IDR 4,541,250.00 |
Ramp Works 2nd
Floor |
7 |
�IDR 465,000.00 |
�IDR 3,255,000.00 |
Total |
�IDR 71,952,233.09 |
Source: Research Results
The total additional costs due to the acceleration of work on the critical
path to structural work amounted to Rp 71,952,233.09 + Rp 28,563,131,560.06 =
Rp 28,635,083.773.15.
Then the time efficiency obtained by using the Critical Path Method (CPM), is:
81 � 74 = 7 days, or
CONCLUSION
There are 18 critical work units
obtained from the results of the analysis using Microsoft Project 2016.
The results of the cost analysis
after accelerating the duration of critical activities obtained the total
duration of structural work for 74 working days with the total cost on
structural work of Rp. 28,635,083.7 7 3.15 and the time efficiency obtained 81
- 74 = 7 days, or 9,46%.
REFERENCES
�Alfianti Erika. (2019).
Optimization of Time and Cost in the Inpatient Building Construction Project of
the Wonoayu Sidoarjo Health Center Using the CPM (Critical Path� Method) Method. Surabaya. Faculty of
Engineering, Bhayangkara University
Aulia M. Zikril.
(2021). Application of the CPM (Critical Path Methid) Method
in the Lau-Simeme Dam Construction Construction Project Package II District,
Deli Serdang. North Sumatra. Faculty of Engineering, University of Muhammadiyah
North Sumatra.
Azizah Nurul. (2017).
Rescheduling of a 2-Storey Office Building Construction Project Using CPM and
PERT Methods at PT. Sources of Successful Ventures. Jakarta. Faculty of
Engineering, Mercubuana University Jakarta.
Ekanugraha. (2016).
Evaluation of Project Implementation Using CPM and PERT Methods (Case Study of
Construction of Binung Baru Terminal in Binung District). Yogyakarta.
Islamic University of Indonesia.
Febriyanto. (2011). Analysis
of CPM and PERT System as Project Efficiency Improvements (CV Case Study. XYZ).
Buoyant. Muhammadiyah Metro Lampung University.
Hardianto the
Great, (2015). Analysis of Time Management Control and Cost of
Hotel Construction Projects with CPM Network (Case Study: Batiqa Hotel
Palembang). Surakarta. Muhammadiyah University of Surakarta.
Kodijah Nyimas
Syarifah, Sugandi Yahdin, and Novi Rustiana Dewi. (2013). Optimization of
the Implementation of the Electric Signaling Construction Project at Kertapati
Station with the Application of the Crash Program Method. Journal of Science
Research, Sriwijaya University, South Sumatra.
Ndraha
Bajisokhi. (2015). User of CPM Method (CRITICAL PATH METHOD) on the
Barus Road Improvement project � Sibolga City Limits. Terrain. Medan Area
University.
Oetomo Wateno. (2014).
Protection and Construction Management of Contemporary Organizations (Part
One). Jakarta. PT. Mediatama Saptakarya.
Prianto, C.
2008.
TA Project Management of Office Building Construction Based on Critical Path
Method Determination. Jakarta. Mercubuana University.
Prayogi Alan
Ambassador. (2015). Acceleration of Scheduling and Time in Building
Buildings Using the Critical Path Method (CPM) and the Evaluation Review
Technique (PERT) program. Malang. Faculty of
Civil Engineering & Planning National Institute of Technology Malang.
Rahayu, Mulyani
& Arpan. (2016). Time Acceleration Analysis With Fast Track Method on
Construction Project Case Study of Ibis Pontianak Hotel Construction Project. Pontianak,
Tanjungpura University Pontianak.
Santosa. (2008), Project
Management : Concept and Implementation. Yogyakarta. Graha Science.
Tardok Eigar
Lamgok. (2018). Time Acceleration Analysis Using CPM and PERT Methods
in the Tanjung Priok Port Pier Construction Project. Surabaya. Sepuluh
Nopember Institute of Technology Surabaya.
Copyright Holders:
Heru Nur Yaqin,
Hanie Teki Tjendani, Budi Witjaksana (2023)
First publication
right:
Devotion - Journal
of Research and Community Service
This article is licensed under
a Creative Commons Attribution-ShareAlike 4.0
International