Text Box: Volume 4, Number 2, February 2023
e-ISSN: 2797-6068 and p-ISSN: 2777-0915

 

 


ANALYSIS OF THE ACCELERATION OF TIME AND COST OF IMPLEMENTING BUILDING CONSTRUCTION PROJECTS USING THE CRITICAL PATH METHOD (CPM) METHOD

 

Heru Nur Yaqin, Hanie Teki Tjendani, Budi Witjaksana

Universitas 17 Agustus 1945 Surabaya, Indonesia

Email: [email protected], [email protected], [email protected]

 

KEYWORDS

cost, duration, CPM, schedule, construction

ABSTRACT

This study aims to obtain the form of project work network in the Probolinggo City Hospital Development Project, to determine the effect of accelerating the duration of Probolinggo City Hospital Development work on network planning and to find out the amount of costs incurred before and after the acceleration of the duration of project work. The method used is the acceleration method with modification of the scheduling of the CPM model. CPM method planning is a recommendation in choosing from many existing methods, because there is a calculation of the earliest time the project starts, the last time the project starts as well as the earliest time to finish and the last time to finish so that it can be known the time lag of all activities. Data Used are primary and secondary data related to the sequence and relationship of activities, implementation time and cost budget plan (RAB). In this thesis, the author takes scheduling data from the Probolinggo City Hospital Development Project which will be used as the basis for writing this thesis in conducting CPM analysis and accelerating the duration of work with additional overtime working hours and calculating the total cost of the acceleration to be used as comparison material in the writing results. Based on the analysis that has been carried out using the Microsoft Project 2016 application, the normal duration of structural work is 81 working days and has 18 critical units of 31 work items. After the acceleration was carried out, there was a decrease in the duration of the work of the structure to 74 working days. The difference in duration decrease was 7 days or 9.45%. The total initial cost with the normal duration for structural work is IDR 28,563,131,560, while after acceleration, the project cost for structural work becomes IDR 28,635,083,793

 

INTRODUCTION

Project scheduling is an activity that sets the timeframe of project activities to be completed, raw materials, labor and time required by each activity. Scheduling is necessary so that project implementation can continue to take place according to the schedule plan that has been made. However, often project scheduling experiences problems, one of which is the occurrence of delays.Scheduling delays can adversely affect quality, time and cost. The construction of the Probolinggo City Hospital was delayed so that there was a minus deviation in progress due to the difference in the time of work implementation between the contractor's offer and those in the contract, resulting in disruption to the start of work implementation and due to the cash flow of underprivileged contractors. It is feared that the retreat of the implementation schedule may interfere with the implementation of the project, therefore it is necessary to accelerate the duration by using the Critical Path Method (CPM) to analyze the acceleration of the duration and its impact on costs.

It is hoped that the results of this research can add insight for students, especially academics, about the analysis of a project using the CPM Method.

It is expected to provide information or recommendations to the relevant institutions (further research) regarding critical pathways and ways to accelerate project implementation, especially in structural work.

It is expected to provide information or recommendations to the owner, implementing contractor and MK consultants regarding critical paths and ways to accelerate project implementation, especially in structural work.

 

Table 1 Previous Research

No

Researchers

Heading

Method

Variable

Conclusion

1

Alan Duta Prayogi, 2015

Acceleration of Scheduling and Time in Building Buildings With Critical Path Method (CPM) and Program Evaluation Review Technique (PERT) (Case Study of Mall Building Project

Based on the anlysis carried out that the duration of the CPM is 427 days with the probability that it can be completed in 427 days is 81.56%.And for acceleration analysis using the Time Cost Trade Off method

Project Cost

In using the Critical Path Method (CPM) and Project Evaluation Review Technique (PERT) methods in the Dinoyo Mall building building, it is to detail the plan and sequence of activities, work, calculate normal time (m), determine optimistic time (a), and pessimistic time (b) on each job, and use the Microsoft Project 2007 application with input

 

According to Husen (2009), a project is a combination of resources such as material people, equipment, and capital / costs that are collected in a temporary organizational forum to achieve goals and objectives.

A project is an effort carried out in a responsible way to produce a product, service that produces a certain result (Lewis, 2005).

Defined as a systematic effort to determine standards that are in accordance with the goals and objectives of planning, designing information systems, comparing implementation with standards, analyzing possible deviations, then carrying out the necessary corrective actions so that resources can be used effectively and efficiently in order to achieve goals and objectives (Mockler, 1972).

Project scheduling is the activity of establishing the timeframe of project activities to be completed, raw materials, labor as well as the time required by each activity.

States that network planning is a tool used to plan, schedule and control the progress of a project. Here are some of the terms used to network the project (Gray and Larson, 2006).

Network Diagram is a visualization of a project based on network planning. Network Diagram is a network that contains the trajectories of activities and sequences of events that exist during the project organizer. Network Diagram consists of activity symbols, event symbols and when necessary symbols of relationships between events (dummy) (Iwawo, 2016).

Defines CPM as a project management model that prioritizes cost as the object being analyzed. CPM is a network analysis that seeks to optimize the total cost of a project through a reduction in the total completion time of the project. The use of the CPM method can save time in completing various stages of a project (Siswanto, 2007).Microsoft Project is software that can be used to design projects and manage the project. The completeness of facilities and its extraordinary ability in processingproject data make this software the most widely used by computer operators because its existence is able to help and facilitate users in completing work, especially identifyingcritical work and related to project data (Setiawan, 2009).

 

RESEARCH METHOD

The research location is located on Jalan Profesor Hamka, Karenglor Village, Kedupak District, Probolinggo City. The research time is two months, starting from October to November 2022.

In this study, the Critical Path method (CPM) method will be used. In this method, there are two kinds of estimated time and cost for each activity. To find out the steps that will be carried out in this study, namely (Heizer and Render, 2015):

1.   Define the project and define the working fractional structure of all structural activities contained in the project;

2.   Determine which activities should be worked on first and which ones should follow the old activities;

3.   Describes a network that connects all activities or creates a network diagram;

4.   Determine the critical path to be used to assist in project scheduling re-planning

 

RESULT AND DISCUSSION

General Project Data

����������� The project that is the object of research is the Probolinggo City Hospital Development Project. The location of the Probolinggo City Hospital Development Project is located on Jalan Profesor Hamka, Karenglor Village, Kedupak District, Probolinggo City.

 

Data Processing

 

Table 2 Detailed Budget Plan Cost of Structural Work Project

No

Types of Work

Total Price

Activity Code

1

Earthworks

 

 

 

Soil Excavation

IDR 111,815,277.99

A

 

Sirtu's Patronage

IDR 1.040.325.000,00

B

 

Urug Sand Under Foundation and Floor t.10 cm

IDR 65,135,945.71

C

 

Working Floor Under Foundation and Floor t.10 cm

IDR 234,605,260.58

D

 

Urugan soil back excavated

IDR 41,266,462.50

And

2

Bottom Structure Work

 

 

 

Stake Work

IDR 3,101,140,000.00

F

 

Pile Cap Foundation Work

IDR 1,320,606,233.03

G

 

Sloof Foundation Work

IDR 3,178,141,803.12

H

 

SFL Basic Lt. Column Work � 1,300

IDR 222,445,986.35

I

 

Basic Lt. Plate Work

IDR 2,483,650,565.36

J

 

Ramp Jobs

IDR 704,382,108.70

K

 

Pit Lift Work

IDR 267,750,000.00

L

 

Stair Work

IDR 151,200,000.00

M

3

Upper Structure Work

 

 

 

1st Floor (One)

 

 

 

Column Work

IDR 671,151,052.44

N

 

Beam Work

IDR 2,548,123,262.00

Or

 

Plate Works Lt.1

IDR 1,825,621,032.15

P

 

Ramp Jobs

IDR 403,115,071.14

Q

 

Stair Work

IDR 151,200,000.00

R

 

2nd (Second) Floor

 

 

 

Column Work

IDR 671,151,052.44

S

 

Beam Work

IDR 2,229,666,948.92

T

 

Plate Works Lt.2

IDR 1,783,229,711.24

In the

 

Ramp Jobs

IDR 403,115,071.14

In

 

Stair Work

IDR 151,200,000.00

In

 

Floor3 (Three)

 

 

 

Column Work

IDR 562,766,457.72

X

 

Beam Work

IDR 1,637,741,918.66

And

 

Plate Works Lt.3

IDR 910,187,676.44

With

 

Ramp Jobs

IDR 284,670,865.28

AA

 

Stair Work

IDR 151,200,000.00

OFF

 

4th (Fourth) Floor

 

 

 

Column Work

IDR 465,738,474.58

AND

 

Beam Work

IDR 608,877,515.50

TO

 

Plate Works Lt.4

IDR 181,910,807.99

AE

Source: Project Data

 

Figure 1 Gantt Chart

Source:Research Results

 

Table 3 Total Slack Based on Microsoft Project 2016

Task Name

Duration

Start

Finish

Total Slack

Predecessors

Structural Work

81 Days

Wed 07/07/21

Sun 26/09/21

 

2.1. Earthworks

40 Days

Wed 07/07/21

Sun 15/08/21

 

A. Soil Excavation

21 Days

Mon 19/07/21

Sun 08/08/21

0 Days

5

B. Sirtu

12 Days

Wed 07/07/21

Sun 18/07/21

0 Days

C. Urug Sand Under Foundation And Floor T.10cm

21 Days

Mon 19/07/21

Sun 08/08/21

48 Days

4ss

D. Foundation Bottom Work Floor And Floor T. 10 Cm

21 Days

Mon 19/07/21

Sun 08/08/21

0 Days

4ss

E. Urugan Soil Back Excavated

14 Days

Mon 02/08/21

Sun 15/08/21

0 Days

7fs-7 Days

2.2. Lower Structure Work

49 Days

Mon 12/07/21

Sun 29/08/21

Piling Work

21 Days

Mon 12/07/21

Mon 02/08/21

0 Days

8sf

Pile Cap Foundation Work

21 Days

Mon 19/07/21

Sun 08/08/21

0 Days

10ss+7 Days

Sloof Foundation Work

35 Days

Mon 26/07/21

Sun 29/08/21

0 Days

11fs-14 Days

Lt Column Work. Sfl Base - 1,300

35 Days

Mon 26/07/21

Sun 29/08/21

65 Days

12ss

Basic Lt Plate Work

35 Days

Mon 26/07/21

Sun 29/08/21

0 Days

12ss

Ramp Jobs

28 Days

Mon 02/08/21

Sun 29/08/21

0 Days

14ss+7 Days

Pek Pit Lift

35 Days

Mon 26/07/21

Sun 29/08/21

65 Days

14ss

Pek Stairs

28 Days

Mon 02/08/21

Sun 29/08/21

0 Days

15ss

2.3. Upper Structure Work

48 Days

Mon 09/08/21

Tue 26/09/21

A. 1st Floor (One)

28 Days

Mon 09/08/21

Sun 05/09/21

 

Column Work

21 Days

Mon 09/08/21

Sun 29/08/21

0 Days

17ss+7 Days

Beam Work

21 Days

Mon 16/08/21

Sun 05/09/21

0 Days

20fs-14 Days

1st Plate Work

21 Days

Mon 16/08/21

Sun 05/09/21

0 Days

21ss

Ramp Jobs

21 Days

Mon 16/08/21

Sun 05/09/21

0 Days

22ff

Pek Stairs

14 Days

Mon 23/08/21

Sun 05/09/21

0 Days

23fs-14 Days

B. 2nd Floor (Two)

35 Days

Mon 16/08/21

Tue 20/09/21

 

Column Work

21 Days

Mon 16/08/21

Sun 05/09/21

0 Days

24ss-7 Days

Beam Work

28 Days

Mon 16/08/21

Sun 12/09/21

0 Days

26ss

2nd Lt Plate Work

21 Days

Mon 23/08/21

Sun 12/09/21

0 Days

27ff

Ramp Jobs

21 Days

Mon 30/08/21

Mon 20/09/21

0 Days

28ss+7 Days

Pek Stairs

7 Days

Mon 30/08/21

Sun 05/09/21

44 Days

29ss

C. 3rd (Third) Floor

35 Days

Mon 23/08/21

Sun 26/09/21

 

Column Work

21 Days

Mon 23/08/21

Sun 12/09/21

37 Days

30ss-7 Days

Beam Work

21 Days

Mon 23/08/21

Sun 12/09/21

37 Days

32ss

3rd Lt Plate Work

21 Days

Mon 30/08/21

Sun 19/09/21

37 Days

33ss+7 Days

Roof Ramp Work

21 Days

Mon 06/09/21

Sun 26/09/21

37 Days

34ss+7 Days

Pek Stairs

7 Days

Mon 13/09/21

Sun 19/09/21

37 Days

35ss+7 Days

D. 4th Floor (Four)

21 Days

Mon 06/09/21

Sun 26/09/21

 

Column Work

14 Days

Mon 06/09/21

Sun 19/09/21

37 Days

36ff

Beam Work

14 Days

Mon 13/09/21

Sun 26/09/21

37 Days

38ss+7 Days

4th Lt Plate Work

7 Days

Mon 20/09/21

Sun 26/09/21

37 Days

39ss+7 Days

Source: Research Results

������ Based on the table above, there is a critical trajectory where the critical trajectory is the one that has a total value of slack = 0.The following is an explanation of the results of the calculation of the total float above:

a.      Critical Path is, a path that has total slack = 0 i.e. , B � D � E � F � G � H � J � K � M � N � O � P � Q � R � S � T � U � V ;

b.     The normal time of completion on the work of the structure is 81 days;

After a critical trajectory is found, and the normal time of completion of the structural work, the next step is to calculate the acceleration of the duration of the work by adding overtime working hours.

 

Accelerating Project Duration

Duration of Work With Additional Overtime Working Hours, For the calculation of the duration of accelerated time is carried out by assuming the amount of duration according to the circumstances in the field. This type of accelerated activity in the Probolinggo City Hospital Development Project is work that is on a critical track.

 

 

 

 

 

 

 

 

 

Table 4 List of Calculations for Adding Overtime Working Hours

Activity Name

Normal Time

Time Accelerated

Time After Accelerated

Additional Overtime (Hours)

Total Overtime Fee Per Day (Rp)

Sirtu

12

4

8

4,000

IDR 260,000.00

Working Floor Under Foundation and Floor t.10 cm

21

7

14

4

IDR 377,500.00

Urugan soil back excavated

14

4

10

3,2

IDR 208,000.00

Stake Work

21

4

14

4

IDR 745,000.00

Pile Cap Foundation Work

21

7

14

4

IDR 745,000.00

Sloop Foundation Work

35

12

23

4,1739

IDR 576,521.74

Basic Lt. Plate Work

35

10

25

3,2

IDR 589,000.00

Ramp Jobs

28

10

25

3,2

IDR 421,000.00

Stair Work

28

10

18

4,4444

IDR 536,111.11

Column Work Lt.1

21

6

15

3,2

IDR 491,000.00

Beam Works 1st Floor

21

7

14

4

IDR 613,750.00

Plate Works Lt.1

21

7

14

4

IDR 648,750.00

Ramp Works 1st Floor

21

7

14

4

IDR 491,250.00

Staircase Works 1st Floor

14

5

9

4,4444

IDR 545,833.33

Column Work Lt.2

21

7

14

4

IDR 613,750.00

Block Works 2nd Floor

28

10

18

4,4444

IDR 681,944.44

Plate Works Lt.2

21

7

14

4

IDR 648,750.00

Ramp Works 2nd Floor

21

7

14

4

IDR 465,000.00

Source: Research Results

 

The next step is to calculate the cost due to the addition of overtime working hours. In the initial planning, the duration for structural work was 81 days with details of structural costs of Rp. 28,563,131,560.06

 

Table 5 List of Cost Calculations Due to Additional Overtime Working Hours

Activity Name

Time Accelerated

Total Overtime Fee Per Day (Rp)

Total Cost After Expedited

Sirtu

4

IDR 260,000.00

IDR 1,040,000.00

Working Floor Under Foundation and Floor t.10 cm

7

IDR 377,500.00

IDR 2,642,500.00

Urugan soil back excavated

4

IDR 208,000.00

IDR 832,000.00

Stake Work

4

IDR 745,000.00

IDR 2,980,000.00

Pile Cap Foundation Work

7

IDR 745,000.00

IDR 5,215,000.00

Sloop Foundation Work

12

IDR 576,521.74

IDR 6,918,260.87

Basic Lt. Plate Work

10

IDR 589,000.00

IDR 5,890,000.00

Ramp Jobs

10

IDR 421,000.00

IDR 4,210,000.00

Stair Work

10

IDR 536,111.11

IDR 5,361,111.11

Column Work Lt.1

6

IDR 491,000.00

IDR 2,946,000.00

Beam Works 1st Floor

7

IDR 613,750.00

IDR 4,296,250.00

Plate Works Lt.1

7

IDR 648,750.00

IDR 4,541,250.00

Ramp Works 1st Floor

7

IDR 491,250.00

IDR 3,438,750.00

Staircase Works 1st Floor

5

IDR 545,833.33

IDR 2,729,166.67

Column Work Lt.2

7

IDR 613,750.00

IDR 4,296,250.00

Block Works 2nd Floor

10

IDR 681,944.44

IDR 6,819,444.44

Plate Works Lt.2

7

IDR 648,750.00

IDR 4,541,250.00

Ramp Works 2nd Floor

7

IDR 465,000.00

IDR 3,255,000.00

Total

IDR 71,952,233.09

Source: Research Results

 

The total additional costs due to the acceleration of work on the critical path to structural work amounted to Rp 71,952,233.09 + Rp 28,563,131,560.06 = Rp 28,635,083.773.15.

Then the time efficiency obtained by using the Critical Path Method (CPM), is:

81 � 74 = 7 days, or

 

CONCLUSION

There are 18 critical work units obtained from the results of the analysis using Microsoft Project 2016.

The results of the cost analysis after accelerating the duration of critical activities obtained the total duration of structural work for 74 working days with the total cost on structural work of Rp. 28,635,083.7 7 3.15 and the time efficiency obtained 81 - 74 = 7 days, or 9,46%.

 

REFERENCES

Alfianti Erika. (2019). Optimization of Time and Cost in the Inpatient Building Construction Project of the Wonoayu Sidoarjo Health Center Using the CPM (Critical PathMethod) Method. Surabaya. Faculty of Engineering, Bhayangkara University

Aulia M. Zikril. (2021). Application of the CPM (Critical Path Methid) Method in the Lau-Simeme Dam Construction Construction Project Package II District, Deli Serdang. North Sumatra. Faculty of Engineering, University of Muhammadiyah North Sumatra.

Azizah Nurul. (2017). Rescheduling of a 2-Storey Office Building Construction Project Using CPM and PERT Methods at PT. Sources of Successful Ventures. Jakarta. Faculty of Engineering, Mercubuana University Jakarta.

Dahlan Ahmad. Evaluation of Time and Cost Control Using Critical Path Method (CPM) and fast Track Method. Hapless. ITN Malang.

Ekanugraha. (2016). Evaluation of Project Implementation Using CPM and PERT Methods (Case Study of Construction of Binung Baru Terminal in Binung District). Yogyakarta. Islamic University of Indonesia.

Febriyanto. (2011). Analysis of CPM and PERT System as Project Efficiency Improvements (CV Case Study. XYZ). Buoyant. Muhammadiyah Metro Lampung University.

Hardianto the Great, (2015). Analysis of Time Management Control and Cost of Hotel Construction Projects with CPM Network (Case Study: Batiqa Hotel Palembang). Surakarta. Muhammadiyah University of Surakarta.

Kodijah Nyimas Syarifah, Sugandi Yahdin, and Novi Rustiana Dewi. (2013). Optimization of the Implementation of the Electric Signaling Construction Project at Kertapati Station with the Application of the Crash Program Method. Journal of Science Research, Sriwijaya University, South Sumatra.

Ndraha Bajisokhi. (2015). User of CPM Method (CRITICAL PATH METHOD) on the Barus Road Improvement project � Sibolga City Limits. Terrain. Medan Area University.

Oetomo Wateno. (2014). Protection and Construction Management of Contemporary Organizations (Part One). Jakarta. PT. Mediatama Saptakarya.

Prianto, C. 2008. TA Project Management of Office Building Construction Based on Critical Path Method Determination. Jakarta. Mercubuana University.

Prayogi Alan Ambassador. (2015). Acceleration of Scheduling and Time in Building Buildings Using the Critical Path Method (CPM) and the Evaluation Review Technique (PERT) program. Malang. Faculty of Civil Engineering & Planning National Institute of Technology Malang.

Rahayu, Mulyani & Arpan. (2016). Time Acceleration Analysis With Fast Track Method on Construction Project Case Study of Ibis Pontianak Hotel Construction Project. Pontianak, Tanjungpura University Pontianak.

Santosa. (2008), Project Management : Concept and Implementation. Yogyakarta. Graha Science.

Tardok Eigar Lamgok. (2018). Time Acceleration Analysis Using CPM and PERT Methods in the Tanjung Priok Port Pier Construction Project. Surabaya. Sepuluh Nopember Institute of Technology Surabaya.

 

Copyright Holders:

Heru Nur Yaqin, Hanie Teki Tjendani, Budi Witjaksana (2023)

 

First publication right:

Devotion - Journal of Research and Community Service

This article is licensed under a Creative Commons Attribution-ShareAlike 4.0 International