Text Box: Volume 4, Number 2, February 2023
e-ISSN: 2797-6068 and p-ISSN: 2777-0915

 

 


SAFETY IMPLEMENTATION ANALYSIS AND OCCUPATIONAL HEALTH AT KRETEK 2 BRIDGE WORK IN BANTUL REGENCY

 

Isyraq Nashrullah Arifin, Wateno Oetomo, Laksono Djoko Nugroho

Universitas 17 Agustus 1945 Surabaya, Indonesia

Email: [email protected], [email protected], [email protected]

 

KEYWORDS

Bridge, Occupational Safety and Health, HIRADC.

 

ABSTRACT

Construction work includes the implementation of construction work and the community organizing the construction work itself. The implementation of this construction work must comply with the provisions regarding engineering, occupational safety and health, labor protection, and local environmental regulations to ensure the realization of an orderly implementation of construction work. The construction of the Kretek 2 Bridge in Bantul Regency, Special Region of Yogyakarta Province has its own challenges, because the location of the bridge is in an area prone to earthquakes and liquefaction or ground movement. With so many workers on this very high-risk project, there is a high probability of an accident occurring. The purpose of the study was to analyze (1) the risky work that could occur in bridge construction work, (2) the work that has the highest possible risk, (3) risk control, (4) the amount of investment costs required. The method used is the HIRADC method. The results of the study were (1) Risky work that can occur was a. High level of risk, including drowning, being dragged by the river current, being hit by heavy equipment maneuvers and falling from a height. b. Moderate risk level, including being crushed by formwork, falling material, scratched hands. c. Low level of risk, including landslides, heavy equipment maneuvers, iron puncture. (2) Work that has the highest possible risk is Pile Cap Excavation Work, Work Floor Work and Pier Head Ironing Work. (3) Risk control in bridge work consists of: Using a boat when measuring in rivers, Conducting briefings before starting activities, Using PPE life vests and placing life ring buoys on boats, Installing signs and placing officers in areas that intersect with roads, Installing guardrail of the project area, installing scaffolding as a working platform and inspecting its feasibility,communicating hazards through signs, conducting refresh training for workers. (4) The investment cost required for implementing K3 on the Kretek 2 Bridge work in Bantul Regency was Rp. 6,545,998,310 or 1.795% of the contract value.

 

INTRODUCTION

Indonesia is one of the developing countries, development and development in the construction sector have increased. The Ministry of Public Works and Public Housing (PUPR) through the Directorate General of Wildlife Development is completing the construction of the Kretek 2 Bridge located in Bantul, Yogyakarta Special Region (DIY). The bridge with a total length of 2.01 km spans the Opak River and connects Tirtohargo Village with Parangtritis Village. This bridge is part of the 1,604 km Long Java South Coast Road which is famous for its coastal tourism area that stretches from Banten to East Java.

The construction of the Kretek 2 Bridge has its own challenges because the location of the bridge is in an area prone to earthquakes and liquefaction or soil movement. With a lot of workers on the project that can be said to be very high-risk, it is not impossible to the possible risk of accidents. In accordance with the requirements of OHSAS 18001, organizations must obtain procedures regarding hazard identification, risk assessment, and determining control or HIRADC for short. This whole process is called risk management. HIRADC is a method used to identify and analyze potential hazards and provide risk assessments that will later be considered regarding the level of danger.

To find out more about the risk of accidents or dangers that will occur and the level of possibility, research is needed that aims to:

1.Analyzing risky work, 2. Analyze the work that has the highest possible risk, 3. Analyzing ways of risk control, 4. Analyzing the large investment costs required for the application of K3 on the Kretek 2 Bridge work in Bantul Regency���

 

RESEARCH METHOD

Occupational Health and Safety (K3)

Occupational Safety and Health (K3) is a condition or factor that affects or may affect the health and safety of workers or other workers (including temporary workers and contractors), visitors, or any person in the workplace. (Ramli, 2013)

Risk

Risk can be associated with the possibility of unintended adverse consequences or uncertainty. This is a condition that causes the growth of risks stemming from various activities and may affect the cost, schedule and quality of projects (Darmawi, 2008)

Danger

�� Danger is a source, situation, or action that could potentially cause human accidents or injuries, damage, or other disturbances. According to Ramli (2010) hazards come from the following five factors: 1.Mechanical Hazard, 2.Electrical Hazard, 3.Physical Hazard, 4.Biological Hazard, 5.Chemical Hazard.

Work Accidents

�� According to the Decree of the Director General of Industrial Relations Development and Manpower Supervision Number 84 of 1998 states that the sources and types of accidents are as follows: 1.Sources of work accidents, 2. Types of accidents

HIRADC (Hazard Identification, Risk Assessment and Determining Control)

�� Ministerial Regulation Number 21/PRT/M/2019 article 3 paragraph 1 states "Every service user and service provider in the implementation of construction services must apply SMKK". Identifying hazards, conducting risk assessments, and conducting risk control are important requirements in the implementation of SMKK.

Data Analysis Techniques

Determination of Respondent Sample

�� The determination of the sample of respondents used is intentional sampling

or purposive sampling (Andriani, 2017). Purposive sampling is sampling whose sample members are selected intentionally based on respondents' knowledge of the risks of implementing K3 work on Kretek Bridge 2 in Bantul Regency.

 

RESULT AND DISCUSSION

Probability Analysis

������ Probability is a measure of the likelihood that a future event will occur. Probability only has a value between 0 and 1. The scale used for this method uses a likert scale, with a range of numbers 1-5 as in the following table:

Table 1 Possibilities with a Likert Scale

Information

Measurements with

Likert Scale

Criterion

Quantitative Criteria

Qualitative Criteria

Very Rare

1

≤ 20

Less occurrence, only under certain conditions

Sometimes It Happens

2

21-40

Sometimes occurs in conditions

certain

May Happen

3

41-60

Occurs under certain conditions

Frequent

4

61-80

Frequent occurrence of every condition

Almost Certainly Happened

5

81-100

Always happens in every condition

����������� Source: Ramli (2013)

2. Impact Analysis with Likert Scale

�������� Impact is an event that exerts an influence, both adverse and beneficial influence. The impact in question is something that will be received or obtained by individual accident victims or companies communally.

Table 2 Impact with a Likert Scale

Information

Measurements with

Likert Scale

Criterion

Quantitative Criteria

Qualitative Criteria

Insignificant

1

≤ 20

Not so significant losses, minor injuries (bad influences can be ignored)

Small

2

21-40

Minor injuries; Requires P3K treatment (directly can be handled at the scene);�� moderate material losses.

Keep

3

41-60

Moderate injuries; Loss of working days; Requires medical treatment; Material losses are considerable

Heavy

4

61-80

Major injuries; Defects result in defects or complete loss of body function,large material losses.

Disaster

5

81-100

Death, huge material losses

Source: Ramli (2013)

3. Severity Index Analysis

������ The severity index is used to determine the significant risks to both items, namely probability and impact. Severity index is calculated using the equation

Severity Index Formula for Probability:

�������������������������������������������������������������� (1)

where:

SI(p)= Severity Index for Probability

ai����������� = Assessment constant

xi������ = Respondent Frequency

i= 1, 2, 3, 4, 5,... n

x1, x 2, x 3, x 4, x5 are respondents' frequency responses

x1= Frequency of respondents "Very Rare," then a1= 1

x2����� = Frequency of respondents "Sometimes It Happens," then a2 = 2

x3����� = Respondent frequency "May Occur," then a3 = 3

x4����� = Frequency of respondents "Frequent Occurrence," then a4 = 4

x5����� = Respondent frequency "Almost Certainly Happens," then a5 = 5

Severity Index Formula for Impact:

���������������������������������������������������������� (2)

where:

SI(i)= Severity Index for Impact

ai������ = Assessment constant

xi����� = Respondent Frequency

i= 1, 2, 3, 4, 5..., n

x1, x 2, x 3, x 4, x5 are respondents' frequency responses

x1= Frequency of respondents "Insignificant," then a1= 1

x2����� = Frequency of respondents "Small," then a2 = 2

x3����� = Frequency of respondents "Moderate," then a3 = 3

x4����� = Frequency of respondents "Weight," then a4 = 4

x5����� = Frequency of respondents "Disaster," then a5 = 5

4. Assessment of Employment Risk Level

������ After obtaining the results of the Severity Index and the level of classification, the matrix value is obtained in accordance with the provisions that have been applied as follows:

Table 3 Category Matrix Possibilities

Category

SI (%)

Possible Matrix Level

Almost Certainly Happened

81-100

5

Frequent

61-80

4

May Happen

41-60

3

Sometimes It Happens

21-40

2

Very Rare

≤ 20

1

Source: Ramli (2013)

 

Table 4 Impact Matrix Categories

Category

SI (%)

Impact Matrix Level

Disaster

81-100

5

Heavy

61-80

4

Keep

41-60

3

Small

21-40

2

Insignificant

≤20

1

Source: Ramli (2013)

������ Once converted into probability and impact matrix levels, the two values are multiplied to plot on the matrix, so that they will get the risk level. The risk level in question is the level of risk obtained from the calculation of the probability that will occur and the amount of influence that will be received. The purpose of this probability and impact matrix is to find out which risks are likely to occur and have a big impact on the project with the scale used is a matrix of values 1-25.

������ To find out the measure of risk, probability and impact can be plotted in a risk matrix, using the equation:

R = P x I (3)������������������������������

where:

R : Leveling Risk

P : Probability

I : Impact

������ The result of the matrix is to determine the risk level from each identification of possible risks that can occur. Then from the known risk level, it will also be taken into account in planning its handling on the risk response.

Determining Control

������ The next stage is to determine the controls used to reduce or eliminate the impact of the risk of imminent harm in a project. Control is carried out based on five levels as follows:

1. Elimination

The method of elimination is a method of risk control that if possible should eliminate or completely remove processes or materials that may cause the presence of harm

2. Substitution �����������

The substitution method is a method of controlling hazards by replacing work or tools with others that have less danger

3. Engineering Control Methods of hazard control that protect workers from hazards such as providing the placement of materials, materials, signs, checking tools and maintenance of tools and materials to be used

4. Administrative (Administrative) Control of risks and hazards in the form of regulations related to occupational safety and health made such as conducting periodic K3 inspections, toolbox meetings, conducting training, safety morning, SOPs and supervision�������

5.Personal Protective Equiepment (PPE) The most recent hazard control is to use personal protective equipment or PPE. This latest hazard control is less effective but must be done for smooth running and safety of work on the condition that you use complete personal protective equipment to minimize workers from being injured

Develop HIRADC (Hazard Identification, Risk Assessment and Determining Control)

������ After collecting various data from hazard identification, risk level assessment and risk control, then compiling a HIRADC able which will be used to determine the value of the risk level of danger that occurs in the bridge pillar structure work as a research object. In able HIRADC made more detailed along with the implementation method to get more detailed results.

 

 

Investment Costs of K3 Implementation

�������� After observation of the application of K3 control, then the calculation of the investment cost needs of the occupational safety and health management system (SMK3) was carried out based on the Circular Letter of the Minister of Public Works Number: 66 / SE / M / 2015, concerning investment costs for the Implementation of the K3 Construction System in the Field of Public Works.

�������� The investment costs required for theimplementation of K3 on the Kretek 2 Bridge work in Bantul Regency include:

1. RKK Setup����������������������������������������������������

2. Socialization, Promotion and training����������

3. Work Protective Equipment and Personal Protective Equipment

4. Insurance and Licensing�������������������������������

5. Construction Safety Personnel����������������������

6. Health facilities and infrastructure���������������

7. Health Programs�������������������������������������������

8. Prevention of Covid-19���������������������������������

9. Handling Covid-19���������������������������������������

10. Signs������������������������������������������������������������

11. Consultation with a Construction Safety expert

12. Miscellaneous Related to K3 Risk Control

13. Industrial Hygiene and Environmental Monitoring��������

14. General and Operational

ANALYSIS

Results of Identification of Risky Work

�������� The risk identification stage is based on the standard of procedure (SOP) of each job. Starting from the implementation stage, the tools used, and the materials used.

Table 5 Results of Identification of Risky Work

No.

Jobs at Risk

Danger

1

Pile Cap Excavation Work

 

1.1

Measurement

a. Danger from the attack of a poisonous animal

b. Mired

c. Struck by lightning

d. Drowning dragged by the current of the river

1.2

Excavation work

a. Landslide

b. Machine maneuvering

2

Work Floor Work

 

2.1

Installation of stakes

a. Hand hit by hammer

b. Respiratory disorders

c. Material fall

2.2

Cleaning and tillage with heavy equipment (Dozzer, excavator, vibro)

a. Exposed to machine maneuvers

b. Respiratory disorders

c. Material fall

2.3

Heap and compaction work

a. Exposed to machine maneuvers

b. Respiratory disorders

c. Material fall

3

Pile cap fixing work

 

3.1

Elevation measurement

a. Exposed to flakes of iron material

b. Fall of iron material

3.2

Installation of stakes

a. Hand hit by hammer

b. Respiratory disorders

c. Material fall

4

Pillar Fixing Work

 

4.1

Scaffolding mounting

a. Scratched hand

b. Stuck

c. Crushed by tools and materials

d. Falling from a height

5

Pier Head Cleaning Work

 

5.1

Elevation measurement

a. Hands scratched iron

b. Pinched hands

c. Falling from a height

6

Iron Fabrication Work

 

6.1

Iron cutting with barbender

a. Electrocuted

b. Fingers of the hand cut off the gear

c. Iron punctured

d. Pinched hands

7

Foundry Works

 

7.1

Casting using mixer truck

a. Mired Mixer Truck

b. Concrete pump mired and rolled over

c. Falling from a height

8

Formwork Installation Work

 

8.1

Installation of bridge pillar formwork

a. Hands scratched iron

b. Hand pinched formwork

c. Exposed to manual work tools

d. Stricken with formwork

e. Dropped from a height

9

Formwork Demolition Work

 

9.1

Formwork Demolition

a. Hands scratched iron

b. Hand pinched formwork

c. Exposed to manual work tools

d. Falling from a height

����������� �� Source: RKK Paket Lot 3 Jembatan Kretek 2 in Bantul Regency

Table 4 shows the results of the identification of the Risk of Kretek Bridge Construction 2 in Bantul Regency, which consists of 9 occupational risks, namely (1) pile cap excavation work, (2) Work floor work, (3) Pile cap fixing work, (4) Pillar cleaning work, (5) Pier head fixing work, (6) Iron fabrication work, (7) Foundry work, (8) Formwork installation work and (9) Formwork demolition work.

Results of the Identification of Risky Work Questionnaire

�������� The assessment was given by 20 respondents who had been determined based on the experience and thoughts of each respondent.

 

Table 6 Results of the Pile Cap Excavation Work Risk Level Questionnaire

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

1

Pile Cap Excavation Work

1.1

 

 

 

Measurement

a. Danger from the attack of a poisonous animal

20

0

0

0

0

20

0

1

5

5

9

20

b. Mired

0

2

2

9

7

20

20

0

0

0

0

20

c. Struck by lightning

20

0

0

0

0

20

0

1

4

5

10

20

d. Drowning dragged by the current of the river

4

4

5

7

0

20

0

3

4

5

8

20

1.2

Excavation work

a. Landslide

8

7

4

1

0

20

10

8

2

0

0

20

b. Machine maneuvering

20

0

0

0

0

20

3

6

4

7

0

20

Source: Data processing results

Table 7 Results of the Work Floor Work Work Risk Level Questionnaire

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

2

Work Floor Work

2.1

 

 

 

Installation of stakes

a. Hand hit by hammer

8

6

5

1

0

20

7

7

5

1

0

20

b. Respiratory disorders

20

0

0

0

0

20

8

7

5

0

0

20

c. Material fall

8

8

3

1

0

20

8

9

2

1

0

20

d. Drowning dragged by the current of the river

8

6

5

1

0

20

7

7

5

1

0

20

2.2

Cleaning and tillage with heavy equipment (Dozzer, excavator, vibro)

a. Exposed to machine maneuvers

7

7

5

1

0

20

2

6

6

6

0

20

b. Respiratory disorders

8

6

4

2

0

20

20

0

0

0

0

20

c. Material fall

9

5

4

2

0

20

9

6

4

1

0

20

2.3

Heap and compaction work

a. Exposed to machine maneuvers

9

5

5

1

0

20

4

5

6

5

0

20

b. Respiratory disorders

9

6

4

1

0

20

20

0

0

0

0

20

c. Material fall

8

7

5

0

0

20

9

9

1

1

0

20

����������������������� Source: Data processing results

Table 8 Pile Cap Fixing Job Risk Level Questionnaire Results

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

3

Pile Cap Fixing Work

3.1

 

 

 

Elevation measurement

a. Exposed to flakes of iron material

8

7

4

1

0

20

20

0

0

0

0

20

b. Fall of iron material

9

8

2

1

0

20

8

8

4

0

0

20

3.2

Installation of stakes

a. Hand hit by hammer

8

5

4

3

0

20

12

6

2

0

0

20

b. Respiratory disorders

8

5

4

1

0

18

20

0

0

0

0

20

c. Material fall

9

7

4

0

0

20

9

8

2

1

0

20

����������������������� Source: Data processing results

Table 9 Results of the Questionnaire on the Risk Level of Pillar Fixing Work

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

4

Pillar Fixing Work

4.1

 

 

 

Scaffolding mounting

a. Scratched hand

7

6

4

3

0

20

7

7

6

0

0

20

b. Pinched hands

7

7

3

3

0

20

8

8

4

0

0

20

c. Crushed by tools and materials

8

5

6

1

0

20

12

6

2

0

0

20

d. Falling from a height

8

7

4

1

0

20

2

2

8

8

0

20

����������������������� Source: Data processing results

Table 10 Pier Head Fixture Work Risk Level Questionnaire Results

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

5

Pier Head Cleaning Work

5.1

 

 

 

Elevation measurement

a. Hands scratched iron

8

6

5

1

0

20

6

6

6

2

0

20

b. Pinched hands

6

6

4

4

0

20

8

8

3

1

0

20

c. Falling from a height

9

5

5

1

0

20

1

1

2

7

9

20

����������������������� Source: Data processing results

Table 11 Results of the Iron Fabrication Work Risk Level Questionnaire

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

6

Iron Fabrication Works

6.1

 

 

 

Iron cutting with barbender

a. Electrocuted

8

6

4

2

0

20

5

5

6

4

0

20

b. Fingers of the hand cut off the gear

6

5

4

5

0

20

8

7

3

2

0

20

c. Iron punctured

8

6

5

1

0

20

9

7

2

2

0

20

d. Pinched hands

5

5

5

5

0

20

7

7

5

1

0

20

����������������������� Source: Data processing results

Table 12 Results of the Foundry Job Risk Level Questionnaire

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

7

Foundry Works

7.1

 

 

 

Casting using mixer truck

a.Mired mixer truck

8

6

5

1

0

20

4

5

5

6

0

20

b. Concrete pump mired and rolled over

8

6

4

2

0

20

6

7

3

4

0

20

c. Falling from a height

10

7

2

1

0

20

3

7

2

8

0

20

����������������������� Source: Data processing results

Table 13 Results of the Questionnaire on the Level of Risk of Formwork Installation Work

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

8

Formwork Installation Work

8.1

 

 

 

Installation of bridge pillar formwork

a. Hands scratched iron

4

4

6

6

0

20

7

7

5

1

0

20

b. Hand pinched formwork

8

6

4

2

0

20

8

7

4

1

0

20

c. Exposed to manual work tools

7

8

4

1

0

20

8

8

1

3

0

20

d. Stricken with formwork

6

5

6

3

0

20

3

7

3

7

0

20

e. Dropped from a height

3

3

7

7

0

20

2

6

5

7

0

20

Source: Data processing results

 

 

Table 14 Results of the Questionnaire on the Level of Risk of Formwork Demolition Work

 

No.

Work

Likelihood

 

Total

Impact

 

Total

Risks of the Stage of Work

1

2

3

4

5

1

2

3

4

5

SJT

KT

DT

ST

HPT

TS

K

S

T

B

9

Formwork Demolition Work

9.1

 

 

 

Formwork Demolition

a. Hands scratched iron

4

4

5

7

0

20

20

0

0

0

0

20

b. Hand pinched formwork

3

4

4

9

0

20

20

0

0

0

0

20

c. Exposed to manual work tools

3

3

6

8

0

20

20

0

0

0

0

20

d. Falling from a height

4

3

4

9

0

20

3

6

3

8

0

20

����������������������� Source: Data processing results

Assessment of the Level of Employment Risk

Table 15 Results of Risk Level Assessment of Pile Cap Excavation Work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

1

Pile Cap Excavation Work

1.1

Measurement

a. Danger from the attack of a poisonous animal

20

100

20%

1

82

100

82%

5

Keep

b. Mired

81

100

81%

5

20

100

20%

1

Keep

c. Struck by lightning

20

100

20%

1

84

100

84%

5

Keep

 

d. Drowning dragged by the current of the river

55

100

55%

3

78

100

78%

4

Tall

1.2

Excavation work

a. Landslide

38

100

38%

2

32

100

32%

2

Low

b. Machine maneuvering

20

100

20%

1

55

100

55%

4

Low

Source: Data processing results

Table 16 Results of the Assessment of the Risk Level of Work Floor Work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

2

Work Floor Work

2.1

Installation of stakes

a. Hand hit by hammer

39

100

39%

2

40

100

40%

2

Low

b. Respiratory disorders

20

100

20%

1

37

100

37%

2

Low

c. Material fall

37

100

37%

2

36

100

36%

2

Low

d. Drowning dragged by the current of the river

39

100

39%

2

40

100

40%

2

Low

2.2

Cleaning and tillage with heavy equipment (Dozzer, excavator, vibro)

a. Exposed to machine maneuvers

40

100

40%

2

86

100

86%

5

Tall

b. Respiratory disorders

40

100

40%

2

20

100

20%

1

Low

c. Material fall

39

100

39%

2

57

100

57%

3

Keep

2.3

Heap and compaction work

a. Exposed to machine maneuvers

38

100

38%

2

82

100

82%

5

Tall

b. Respiratory disorders

37

100

37%

2

20

100

20%

1

Low

c. Material fall

37

100

37%

2

39

100

39%

2

Low

Source: Data processing results

Table 17 Pile Cap Fixing Work Risk Level Assessment Results

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

3

Pile Cap Fixing Work

3.1

Elevation measurement

a. Exposed to flakes of iron material

38

100

38%

2

20

100

20%

1

Low

b. Fall of iron material

35

100

35%

2

56

100

56%

3

Keep

3.2

Installation of stakes

a. Hand hit by hammer

42

100

42%

3

40

100

40%

2

Keep

b. Respiratory disorders

34

90

38%

2

20

100

20%

1

Low

c. Material fall

35

100

35%

2

45

100

45%

3

Keep

����������� Source: Data processing results

Table 18 Results of the Risk Level Assessment of Pillar Fixing Work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

4

Pile Cap Fixing Work

4.1

Elevation measurement

a. Scratched hand

43

100

43%

3

39

100

39%

2

Keep

b. Pinched hands

42

100

42%

3

36

100

36%

2

Keep

c. Crushed by tools and materials

40

100

40%

2

30

100

30%

2

Low

d. Falling from a height

38

100

38%

2

62

100

62%

4

Keep

����������� Source: Data processing results

Table 19 Pier Head Cleaning Work Risk Level Assessment Results

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

5

Pier Head Cleaning Work

5.1

Elevation measurement

a. Hands scratched iron

39

100

39%

2

44

100

44%

3

Keep

b. Pinched hands

46

100

46%

3

37

100

37%

2

Keep

c. Falling from a height

38

100

38%

2

82

100

82%

5

Tall

����������� Source: Data processing results

Table 20 Results of the Risk Level Assessment of Iron Fabrication Work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

6

Iron Fabrication Works

6.1

Elevation measurement

a. Electrocuted

40

100

40%

2

49

100

49%

3

Keep

b. Fingers of the hand cut off the gear

48

100

48%

3

39

100

39%

2

Keep

c. Iron punctured

39

100

39%

2

37

100

37%

2

Low

d. Pinched hands

50

100

50%

3

40

100

40%

2

Keep

����������� Source: Data processing results

Table 21 Results of the Assessment of the Level of Risk of Foundry Work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

7

Foundry Works

7.1

Casting using mixer truck

a.Mired mixer truck

39

100

39%

2

53

100

53%

3

Keep

b. Concrete pump mired and rolled over

40

100

40%

2

45

100

45%

3

Keep

c. Falling from a height

34

100

34%

2

55

100

55%

3

Keep

����������� Source: Data processing results

 

Table 22 Results of the assessment of the level of risk of formwork installation work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

8

Formwork Installation Work

8.1

Installation of bridge pillar formwork

a. Hands scratched iron

54

100

54%

3

40

100

40%

2

Keep

b. Pinched hands

40

100

40%

2

38

100

38%

2

Low

c. Exposed to manual work tools

39

100

39%

2

39

100

39%

2

Low

d. Stricken with formwork

46

100

46%

3

54

100

54%

3

Keep

e. Dropped from a height

58

100

58%

3

57

100

57%

3

Keep

Source: Data processing results

Table 23 Results of the Assessment of the Risk Level of Formwork Demolition Work

 

No

Work

 

SI(p)

Level

Prob.

 

SI (i)

Level

Impact

Level

Risk

Risks of the Stage of Work

9

Formwork Demolition Work

9.1

Formwork Demolition

a. Hands scratched iron

55

100

55%

3

20

100

20%

1

Low

b. Hand pinched formwork

59

100

59%

3

20

100

20%

1

Low

c. Exposed to manual work tools

59

100

59%

3

20

100

20%

1

Low

d. Falling from a height

58

100

58%

3

56

100

56%

3

Keep

Source: Data processing results

Grouping of Employment Risk Levels

Grouping of Employment Risk Levels

�������� Based on the assessment of the risk level for each work, the project on the Kretek 2 Bridge construction project in Bantul Regency obtained a grouping of high to low risk levels for each work as follows:

Table 24 Grouping of Employment Risk Levels

No

Work

Job Risk

Level

Prob.

( P )

Level

Impact

( I )

Level

Risk

(P x I)

Job Risk

1

Pile Cap Excavation Work

 

 

 

 

Tall

Drowning dragged by the current of the river

3

4

12

Keep

Mired

5

1

5

 

Danger from the attack of a poisonous animal

1

5

5

 

Struck by lightning

1

5

5

Low

Landslide

2

2

4

 

 

Machine maneuvering

1

4

4

2

Work Floor Work

 

 

 

 

Tall

Exposed to machine maneuvers

2

5

10

Keep

Material fall

2

3

6

Low

Hand hit by hammer

2

2

4

Material fall

2

2

4

 

 

Drowning dragged by the current of the river

2

2

4

 

 

Respiratory disorders

2

1

2

3

Pile Cap Fixing Work

 

 

 

 

Keep

Hand hit by hammer

3

2

6

 

 

Material fall

2

3

6

 

Low

Exposed to flakes of iron material

2

1

2

 

 

Respiratory disorders

2

1

2

4

Pillar Fixing Work

 

 

 

 

Keep

Scratched hand

3

2

6

 

 

Pinched hands

3

2

6

 

 

Dropped from a height

2

2

4

 

Low

Crushed by tools and materials

2

2

4

5

Pier Head Cleaning Work

 

 

 

 

Tall

Dropped from a height

2

5

10

 

Keep

Pinched hands

3

2

6

 

 

Hands scratched iron

2

3

6

6

Iron Fabrication Works

 

 

 

 

Keep

Fingers of the hand cut off the gear

3

2

6

 

 

Electrocuted

2

3

6

 

Low

Iron punctured

2

2

4

7

Foundry Works

 

 

 

 

Keep

Mired mixer truck

2

3

6

 

 

Concrete pump mired and rolled over

2

3

6

 

 

Dropped from a height

2

3

6

8

Formwork Installation Work

 

 

 

 

Keep

Crushed by formwork

3

3

9

 

 

Dropped from a height

3

2

6

 

 

Hands scratched iron

3

2

6

 

Low

Exposed to manual labor tools

2

2

4

9

Formwork Demolition Work

 

 

 

 

Keep

Dropped from a height

3

3

9

 

Low

Hands scratched iron

3

1

3

 

 

Hand pinched formwork

3

1

3

 

 

Exposed to manual labor tools

3

1

3

����������� Source: Data processing results

Based on the grouping of occupational risk levels, the construction of Kretek Bridge 2 in Bantul Regency obtained 3 (three) high job risks, 12 (twelve) medium occupational risks and 9 (nine) low job risks.

Risk Control and Preparation of HIRADC

�������� The next stage is to determine the control and preparation of the HIRADC table used to reduce or eliminate the impact of the risk of hazards that will occur on the nine bridge pillar structure works in the Kretek 2 Bantul Bridge Construction, as follows:

 

CONCLUSION

Based on the objectives of the study, it can be concluded that:

The risky work that can occur in the construction of the Kretek Bridge 2 pillar structure in Bantul Regency is as follows:

High risk levels include: 1. Drowning dragged by river currents, 2. Exposed to machine maneuvers and 3. Dropped from a height

Moderate risk levels include: 1. Being crushed by formwork, 2. Falling material, 3. Scratched hand, 4. Pinched hand, 5. Hand hit by hammer, 6. Fingers of hand cut gear, 7. Electrocuted, 8. Mired mixer truck, 9. Concrete pump mired and rolled over, 10. Mired, 11. Danger from the attack of a poisonous animal and 12. Struck by lightning

Low risk levels include: 1. Landslides, 2. Maneuvering heavy equipment, 3. Punctured iron, 4. Exposed to manual work tools, 5. Crushed tools and materials, 6. Hand pinched formwork, 7. Exposed to manual work tools, 8. Exposed to flakes of iron material and 9. Respiratory disorders

In the implementation of construction, works that have a high potential risk are: 1. Pile Cap Excavation Work, 2. Work Floor Work and 3. Pier Head's Fixing Work.

Risk control on the work of Kretek 2 Bridge in Bantul Regency is as follows:

Control of the risk of drowning dragged by river currents in pile cap excavation work, consisting of: 1. Use of boats when measuring on the river, 2. Conduct briefings before starting activities and 3. Using PPE life vest and placing life ring buoy on the boat

Control of the risk of being exposed to machine maneuvers on work floor work, consisting of: 1. Installation of signs and placement of officers in areas that intersect with the highway and 2. Installation of project area guardrails

Control of the risk of falling from a height on pier head cleaning work, consisting of: 1. Installing the scaffolding as a working platform and inspecting its airworthiness and 2. Hazard communication through signs, 3. Refresh training for workers

The investment cost required for the application of K3 on the Kretek 2 Bridge work in Bantul Regency amounted to Rp 6,545,998,310 (six billion five hundred and forty-five million nine hundred ninety-eight thousand three hundred and ten rupiah) or 1.795% of the contract value of Rp 364,627,810,221, in accordance with the Regulation of the Minister of Public Works Number: 05/PRT/M/2014, which includes:

The implementation of construction with high and low hazard potential must involve a construction K3 Expert (Article 6 of the Pu Regulation Number: 05 / PRT / M / 2014)

The cost of organizing SMK3 Construction PU Field is allocated in general costs which include: a. RKK Preparation, b. Socialization, Promotion and training, c. Work Protective Equipment and Personal Protective Equipment, d. Insurance and Licensing, e. Construction Safety Personnel, f. Health Facilities and infrastructure, g. Health Programs, h. Prevention of Covid-19, i. Handling of Covid-19 (SE No. 443/5283 of 2021), j. Signs, k. Consultation with experts related to Construction Safety, l. Miscellaneous Related to K3 Risk Control, m. Industrial Hygiene, Environmental Management and Monitoring and n. General and Operational (Article 20 of the Pu Regulation Number: 05/PRT/M/2014)

Hazard Identification, Risk Assessment, Priority Scale, K3 Risk Control (Appendix to Pu Regulation Number: 05/PRT/M/2014).

 

REFERENCES

Andriani, Durri. (2017). Research Methods. Jakarta: Pratasejati Mandiri

AS/NZS 4360. (1999). Risk Management Guidelines. Sidney: Strathfield NSW2135.

AS/NZS 4360. (2004). Risk Management Guidelines. Sidney: Strathfield NSW2135.

Darmawi, Herman. (2008). Risk Management. Jakarta: Bumi Aksara.

OHSAS 18001. (2007). Occupational Safety and Health Management System. Translation by Jack Matatula. Independent Business.

OHSAS 18002. (2008). K3 Management System Requirements. OHSAS Project Group

Regulation of the Minister of Public Works Number: 50/M /2014 concerning Special Construction of Public Works. Department of Public Works, Jakarta

Regulation of the Minister of Manpower Number PER.05 / MEN / 1996 of 1996 concerning Occupational Safety and Health Management System. Occupational Safety and Health

Regulation of the Minister of Manpower of the Republic of Indonesia No. 26 of 2014 concerning the Implementation of the Assessment of the Implementation of the Occupational Safety and Health Management System.

Regulation of the Minister of Public Works and Public Housing Number 21/PRT/M/2019. About Construction Safety Management System Guidelines.

Regulation of the Minister of Public Works and Public Housing Number 10 of 2021. About Occupational Safety and Health Management System

Regulation of the Minister of Manpower Number: PER.05/MEN/1996. About Occupational Safety and Health Management System.

Regulation of the Minister of Manpower of the Republic of Indonesia. Number: PER.03/MEN/1998. About Procedures for Accident Reporting and Accident Inspection

Government Regulation of the Republic of Indonesia Number 50 of 2012 concerning the Implementation of Occupational Safety and Health Management System.

Ramli, Soehatman. (2010). Practical Guidelines for Fire Management. Jakarta: Dian Rakyat

Ramli, Soehatman. (2013). Smart Safety: A Guide to Effective Implementation of SMK3. Jakarta: Dian Rakyat

Law of the Republic of Indonesia Number 3 of 1992. On Social Security of Labor.

Law of the Republic of Indonesia No.1 of 1970 concerning Work Safety.

 

 

Copyright Holders:

Isyraq Nashrullah Arifin, Wateno Oetomo, Laksono Djoko Nugroho (2023)

 

First publication right:

Devotion - Journal of Research and Community Service

This article is licensed under a Creative Commons Attribution-ShareAlike 4.0 International