Gayatri Nuansa Putri, Herto Dwi Ariesyadi
Faculty of Civil and
Environmental Engineering, Institute Teknologi Bandung, Indonesia
Email: [email protected]
KEYWORDS risk
management; HOR; lifting; transmission pipeline |
ABSTRACT The need for gas in Indonesia is currently quite urgent, but the
infrastructure to provide natural gas supplies for industry is inadequate, so
the government is encouraging the development of national natural gas
infrastructure. In this project, build facilities including Tie-in at the
Onshore Receiving Facilities (ORF) and then build a pipeline. The ORF
consists of various large instruments, the installation process of which
requires the assistance of heavy equipment such as a crane. Instrument
installation work at ORF using a crane is included in the critical &
extreme risk because the placement will use more than one crane and this work
is carried out on a platform. Apart from that, the ORF was built next to an
existing LPG station, so this condition has its own potential danger. To
find out the source of the biggest risks, risks that may occur, methods of
risk mitigation, and the level of effectiveness of the mitigation provided,
occupational safety and health risk management analysis could be carried out
using the House of Risk (HOR) and Hazard Identification, Risk Assessment
& Determining Control (HIRADC) method. Lifting activities on the ORF
platform was the biggest source of danger and there were 15 possible risks
that may occur, 3 risk agents were in the mobilization of heavy equipment
activities (cranes), 5 risk events were in the crane placement activities and
7 risk events were from material transport activities and there were 36 risks
agents in it, 9 risk agents for mobilization activities, 11 risk agents for
crane placement activities and 14 risk agents for material
transport activities. Of the 36 risk agents, 16 of them have high
potential, so suggestions for risk mitigation actions were given using the
HOR phase II method. By conducting discussions, there were 48 mitigation
action plans that were able to reduce the potential of risk agents with 36
main preventive actions, namely suggestions for mitigation actions that had
difficulty value 3 or easy to implement. After assessing the recommended
preventive actions, an assessment is carried out that there was a reduction
in the level of risk using the Hazard Identification, Risk Assessment &
Determining Control (HIRADC) method, where there were 3 medium risk
categories and 13 low-risk categories. Before recommendations for risk
mitigation actions, there were 3 extreme risk categories and 13 high
risk categories. |
INTRODUCTION
Currently,
the need for gas is quite urgent, but the infrastructure for supplying natural
gas to industry is inadequate, so the government is encouraging the development
of national natural gas infrastructur (Umah, 2021). One of
them is the Semarang - Batang section of the natural gas transmission pipeline
which includes tie-ins at the Semarang Onshore Receiving Facillities (ORF)
facility and the pipeline to the Batang Integrated Industrial Zone (KITB) area.
The ORF facility itself consists of various large instruments, so the
instrument installation work at ORF is included in critical & extreme risk
where lifting work at ORF will use more than one crane (tandem crane) where
this work will be carried out on a platform and next to the existing LPG station (Basuki, 2023).
Instrument
lifting work has the potential for fatalities, property damage, lost time
injury and environmental pollution. Work accidents in the tandem lifting
process have occurred due to several factors, including the negligence of
workers who do not work according to the SOP, lack of preparation in lifting
activities so that the position of the crane becomes unstable, due to a
collision between two cranes, due to the fall of a girder in a domino manner,
and failure in determine the carrying load (Adomaitis, 2017; Dutch Safety Board,
2016; OSHA, 2012, 2018, 2021).
Seeing the
potential for work accidents in lifting work using cranes, it can be assessed
that lifting activities require a risk management system. Based on International
Organization for Standardization (2018) the assessment process of risk management
itself is divided into three parts, namely risk identification, risk analysis
and risk evaluation. Cranes play a major role in various construction
accidents, so evaluation is necessary. In this journal, a crane evaluation was
carried out using the Failure Modes and Effects Analysis (FMEA) method and the
results obtained that the biggest factors of crane accidents were heavy loads
and working height (Sadidi et al., 2016). Another
study that identified the failure of a crane used the Failure Modes and Effects
Analysis (FMEA) method and said that many failures in crane operation were
caused by the condition of the crane that was not prim (Strohmandl et al., 2019). Based on
these two studies using the FMEA method, where the research carried out is
limited to hazard identification and risk analysis without preventive risk
management. Once a risk management plan is in place, the identified and
analyzed hazards can be compiled to form the basis of an effective risk
mitigation strategy. in previous research entitled Hazard Identification &
Risk Assessment in Construction Industry by Chauhan (2018) where in
the journal it is stated that the Hazard Identification & Risk Assessment
method can be used for risk identification, risk analysis and risk evaluation.
HIRDC can also be used to group existing risks. Risk Assessment in construction
activities can also be assessed using the House of Risk (HOR) method as in
previous research conducted by (Muntoha, 2019). In
general, the HOR method can be used to carry out risk assessments to provide
risk mitigation suggestions from construction activities.
In this
study, to find out the biggest source of risk, risks that may occur, ways of mitigating
risk handling and the level of effectiveness of the recommendations provided,
an analysis of occupational safety and health risk management will use the HOR
(House of risk) method. This HOR method is a development of FMEA and HOQ
methods, based on research these methods are considered to be able to include
an integrated risk management analysis, where the HOR phase I method will
determine the priority level of risk agents that must be controlled and for the
HOR phase II method will determine the priority of mitigation actions that can
be carried out (Nyoman Pujawan & Geraldin, 2009). With the
recommended risk priorities and mitigation priorities, an assessment of
possible risk reduction can be carried out using the Hazard Identification,
Risk Assessment & Determining Control (HIRADC) method.
RESEARCH
METHOD
Identify potential
hazards and causes of hazards
Identifying
potential dangers and causes of danger begins by searching for secondary data
that can identify potential dangers and causes of danger. Potential hazards and
possible causes of harm will be scored based on the level of likelihood
(occurrence), severity (Severity) and the correlation between the two. This
assessment was carried out using a questionnaire given to 35 workers who had
job relevance.
The
technique used in determining the sample is by using a non-probability
purposive sampling technique, this technique is carried out by taking a
non-probability sample where the unit is selected because the unit has the
characteristics needed in the sample (Fauzy, 2019; Parveen & Showkat,
2017). The
respondents who were sampled were workers in the HSE and construction
departments. Sampling was carried out on office workers and field workers.
Risk assessment
is carried out based on AS/NZS 4360 1999 which has been modified by (Iskandar, 2022). Questionnaire
House of risk phase I
Severity,
occurrence and correlation values can be used for phase I HOR calculations
with output in the form of ARP values or potential risk agents. The HOR I
method will use formula 1.
(1)
Information:
= Potential risk agents
=Possible Value (Occurrence)
=Severity Value (Severity)
= Correlation Value between Possibility Value and Severity Value
House of risk phase II
Potential
risk agents (ARP) obtained will be given risk mitigation suggestions which can
be assessed using the House of risk phase II method. Identification of relevant
mitigation actions is carried out through a literature study process and then
discussed by related parties. The mitigation action points obtained were
measured by measuring the correlation and the level of difficulty for its
application through discussions and interviews.
The
correlation value and implementation difficulties have been known, phase II HOR
calculations are carried out with the output in the form of priorities in
taking effective action (preventive action). The HOR II method will calculate
the level of effectiveness and total effectiveness.
(2)
Information:
= Potential risk agents
=Effectiveness level
= Correlation value between potential risk agents and recommended
mitigation actions
(3)
Information:
= Total Effectiveness
=Effectiveness level
= Difficulty level of implementation
HIRADC
In this
study the HIRADC method was carried out to see the potential risk reduction
found in the HOR phase I method. Then a mitigation action plan was carried out
in the HOR Phase II method, in the HIRADC method an assessment of potential
risk reduction and risk grouping was carried out.
The risks
that will be calculated in the HIRADC table used are priority risks obtained
from the ARP calculation of the House of risk I method and the controls used
are priority control results from the House of risk II method.
Analysis of
Results and Discussion
This
results analysis step is carried out after collecting, summarizing and
processing the data. The results of this research data processing are then
analyzed and interpreted to draw conclusions that are in accordance with the
research objectives regarding risk management analysis in the Semarang – Batang
Natural Gas Transmission Pipeline Development Project.
RESULTS AND
DISCUSSION
Identification of
hazards and causes of hazards.
This hazard
identification uses the history of work accidents that occurred from the start
of the project to April 2023. During the course of this project there were 4
work accidents including 1 property damage and 3 near misses. Based on history,
there were 2 work accidents which were divided into near-miss and property
damage that occurred in lifting activities for both loading and unloading
material activities, 1 near-miss occurred in mobilization activities and 1
near-miss occurred during drilling activities using the HDD system. So lifting
activities are the biggest source of risk that can occur.
Based on
the results of literature studies and field observations, 15 risk events were
found in instrument lifting activities on platforms. Lifting activities are divided
into three activities, namely mobilization, crane placement and lifting
activities. There are risk events in these three activities, in mobilization
activities there are 3 risk events, in crane placement activities there are 5
risk events and there are 7 risk events in lifting activities. The details of
risk events observed for lifting activities are listed in Table 1.
Table 1. Risk Events
RISK CODE |
RISK EVENTS |
Mobilization Activities |
|
E1 |
Traffic accident |
E2 |
Hit an immovable object |
E3 |
Burn out syndrome |
Crane Placement
Activities |
|
E4 |
Pinched tool |
E5 |
Scratched/punctured |
E6 |
Ergonomics |
E7 |
Cranes hit an existing station |
E8 |
Getting hit by equipment |
Appointment Activities |
|
E9 |
Crushed material |
E10 |
Hit by swing crane |
E11 |
Get caught up in the tagline |
E12 |
Heavy equipment overturned |
E13 |
Explode |
E14 |
Fire |
E15 |
The instrument overwrites the existing station |
Based on
the results of the questionnaires given to workers who are placed in offices
and fields, the results are slightly different, this is the risk event number
E2, E3 and E4. The background that makes the difference in the assessment can
be caused by several factors such as minimal worker skills and knowledge,
educational background, and previous work experience.
In
mobilization activities, there are three possible events that can affect risk,
including traffic accidents, cranes or heavy equipment hitting immovable
objects, and burn out syndrome. Traffic accidents that occur involving heavy
equipment often occur, one of which is a collision between the B-9387-PD crane
car and the KLB KP/10084 Train, Banyuwangi – Madiun Department, this happened
in July 2014 (Dan & Jalan, 2021). Heavy
equipment that has hit immovable objects has also occurred, one of which is the
Rafter Crane which crashed into a resident's house during the mobilization
process in Labuan Bajo (Ninu, 2022) and a truck crane accident that hit an
electricity pole (Zulfahmi, 2022). Burn out
syndrome can be caused by working too much as a result of working on a project
late. Delays in work can be caused by material delays and factors that
influence them as stated (Kurniawan & Rudi, 2019). that
there are six factors of delay in project work, one of which is the delay in
delivery or provision of equipment
In the
crane placement activity, it is divided into several activities, including
parking the crane, placing outrigger pads, and installing outriggers. Of the
total activities, there are five possible events that can affect the risk,
including equipment being pinched, scratched/punctured, ergonomics, the crane
hitting an existing station, and the possibility of workers being hit by
equipment. The first possible event is the worker being pinched by a tool or
equipment that may occur, especially during the outrigger installation process.
The possibility of scratches and punctures is also very possible during the
process of fitting the outriggers or when installing the outriggers because the
work is done manually. The possibility of ergonomic errors during the process
of placing outrigger pads is very likely to occur because the work is done
manually and the weight of the outrigger pads is quite large. The crane parking
process is very possible if the crane hits an existing station where the crane
is placed close to the existing station so a good distance estimate is needed
when placing the crane. The possibility of workers being hit by equipment may
happen. This has happened to workers in Hong Kong who died because they were
hit by a gentry crane (Cheng, 2023).
In lifting
activities, there are seven possible events that can affect the risk, including
being crushed by material, being hit by a crane swing, being entangled in
taglines, heavy equipment being overturned, exploding, catching fire, and
instruments falling on existing stations. These possibilities make it possible
to occur simultaneously or have a relationship between one another like a
domino effect. Like heavy equipment that is overturned, this can cause the
material on it to fall on workers and the surrounding environment where in this
project work there is an existing station, and if the material or heavy
equipment that is overturned hits the existing gas station, it is possible for
an explosion to occur and the explosion can result in a fire (OSHA, 2021).
Occupational accidents due to being entangled in a crane tagline have the
possibility of occurring and the incident of workers getting entangled in a
crane tagline has occurred in construction work in Toronto, where a rigger who
is responsible for ensuring the material load is securely tied before being
lifted hangs high in the air for quite a long time, this is because The worker
was entangled in the crane's tagline rope, resulting in the worker suffering
injuries (Houghton, 2022).
Based on
the 15 existing risk events, there are 36 risk triggers (risk agents), there
are 9 risk agents in mobilization activities, 11 risk agents in caren placement
activities, and 14 risk agents in appointment activities. The details of the
risk agent description are in Table 2.
Table 2.
Risk Agent
No |
Activity |
Risk Agent |
Code |
1 |
Mobilization |
Drivers drive more than the specified speed limit |
A1 |
2 |
Drivers lose concentration due to fatigue/drowsiness |
A2 |
|
3 |
Driving duration is not proportional to the driver's
ability |
A3 |
|
4 |
Driver driving drunk |
A4 |
|
5 |
Bad weather |
A5 |
|
6 |
Heavy traffic conditions |
A6 |
|
7 |
The worker who will make the delivery does not work
on time |
A7 |
|
8 |
There is material that is not suitable/damaged so
that it requires replacement/additional material |
A8 |
|
9 |
Delivery does not use escort |
A9 |
|
10 |
Placement of Cranes |
Operators lose concentration due to
fatigue/drowsiness |
A10 |
11 |
The duration of work is not proportional to the
operator's abilities |
A11 |
|
12 |
Operators/workers work in a drunken state |
A12 |
|
13 |
Bad weather |
A13 |
|
14 |
Operators/workers are not skilled in installing
outrigger beams |
A14 |
|
15 |
The operator did not implement the SOP for
installing the outgerbeam |
A15 |
|
16 |
Workers do not use PPE (gloves) |
A16 |
|
17 |
Workers do not pay attention to posture when
lifting/installing the steel plate/crane mate |
A17 |
|
18 |
The parking process is carried out backwards so that
the driver cannot see and calculate the distance |
A18 |
|
19 |
There is no area limit |
A19 |
|
20 |
Crane maneuvering too fast/hard |
A20 |
|
21 |
The road to be traversed is small/narrow |
A21 |
|
22 |
Material Lift |
Operators lose concentration due to
fatigue/drowsiness |
A22 |
23 |
The duration of work is not commensurate with the
ability of the operator/reager |
A23 |
|
24 |
Operator/Reager working drunk |
A24 |
|
25 |
Bad weather |
A25 |
|
26 |
Crane maneuvering too fast/hard |
A26 |
|
27 |
Lifting work does not comply with the SOP/lifting
plan |
A27 |
|
28 |
The binding work is not in accordance with the SOP |
A28 |
|
29 |
One of the operators misinterpreted the signalman's
sign |
A29 |
|
30 |
The speed of raising/lowering the sling is not the
same |
A30 |
|
31 |
Cargo load exceeds capacity |
A31 |
|
32 |
Poor sling/tagline quality |
A32 |
|
33 |
Ragers/workers are not aware of the tagline behind
workers |
A33 |
|
34 |
Slanted platforms |
A34 |
|
35 |
The platform collapsed |
A35 |
|
36 |
Sparks from friction between iron (material and
existing pipes) |
A36 |
All of the risk
agents were identified and grouped into 4 risk factors including human error,
work environment factors, mechanics and ergonomics. Based on the 36 existing
risk triggers, of which 17 risk triggers are based on human error factors, 7
risk triggers are based on work environment factors, 11 are based on mechanics
and 1 risk trigger is based on ergonomic attitudes. The detailed grouping of
risk agents can be seen in Table 3.
Table 3. Grouping Risk Agent
Factor |
Risk Agent |
Human
error |
A1, A2, A3, A4,
A7, A10, A11, A12, A14, A15, A16 A22, A23, A24, A29, A30, A33 |
Mechanic |
A8, A9, A18,
A20, A21, A26, A27, A28, A31, A32, A36 |
Work
environment |
A5, A6, A13,
A19, A25, A34, A35 |
Ergonomics |
A17 |
Based on
the results of the questionnaires given to workers who are placed in offices
and fields, there are differences of opinion between the two, this is in risk
agent numbers A2, A4, A9, A10, A12, A21, A22, and A24. The difference in these
assessments can be based on several factors such as minimal worker skills and
knowledge, educational background, and previous work experience. This is in
line with the domino theory that the social or genetic environment is a factor
before an accident occurs, this theory was put forward by Heinrich (Handayani, 2020), and
reinforced by the tripod theory that accidents are related to dangerous
behavior, one example of which is high workload, excessive time constraints and
inappropriate perception of danger, this theory was put forward by Reason in
1990 (Pratama, 2021).
House of risk Phase I
Aggregate
Risk Potential (ARP)
is a calculation process from the HOR Phase I method where this ARP calculation
will produce the most potential risks from lifting activities on the platform.
The ARP calculation focuses on three factors, namely occurrence, severity and
interrelationship. From the sum of the ARP values, cumulative frequency
calculations are carried out using the Pareto diagram.
Figure 1. Risk
agent Priority Pareto Diagram
Based on
the Phase I HOR calculation, 16 potential risk agents were obtained as priority
risks for risk mitigation. The 16 priority risk agents can be seen in Table 4
Based on
the results of the potential risk agents obtained, 3 risk agents were found
that could potentially occur in mobilization activities, namely A2, A3 and A5.
There are 6 risk agents that have the potential to occur in crane placement
activities, namely A10, A14, A15, A16, A17, A18 and there are 7 risk agents
that have the potential to occur in material lifting activities, namely A20,
A21, A22, A27, A28, A29 and A32.
Table 4. The results of
ranking the ARP value using a Pareto diagram
Code |
Frequency (ARP Value) |
Cumulative Frequency |
% Cumulative Frequency |
A10 |
319.0 |
319.0 |
11.0 |
A27 |
305,2 |
624.2 |
21,6 |
A32 |
243.1 |
867.2 |
30.0 |
A22 |
218.6 |
1085.8 |
37.6 |
A2 |
184.1 |
1269.9 |
43.9 |
A28 |
171.4 |
1441.3 |
49.9 |
A21 |
146.7 |
1588.0 |
54.9 |
A16 |
134.8 |
1722.8 |
59.6 |
A17 |
107,8 |
1830,5 |
63.3 |
A20 |
99.5 |
1930.0 |
66,8 |
A18 |
91.3 |
2021,4 |
69.9 |
A29 |
83.0 |
2104.4 |
72.8 |
A5 |
70.5 |
2174,9 |
75.3 |
A3 |
69.1 |
2244.0 |
77.7 |
A14 |
56,8 |
2300.8 |
79.6 |
A15 |
55.5 |
2356,3 |
81.5 |
Based on
the results of the potential risk agents obtained, 3 risk agents were found
that could potentially occur in mobilization activities, namely A2, A3 and A5.
There are 6 risk agents that have the potential to occur in crane placement
activities, namely A10, A14, A15, A16, A17, A18 and there are 7 risk agents
that have the potential to occur in material lifting activities, namely A20,
A21, A22, A27, A28, A29 and A32. In general, the 16 potential risk agents said
that crane accidents were caused by several factors, namely due to errors made
by operators and/or riggers, especially related to: overloading the crane,
collision/interaction between two cranes on the same construction site (A2 ,
A3, A10, A14, A20, A21, A22, A29), then crane accidents often occur due to
errors in lifting, turning, or assembly/disassembly of large components (A15,
A16, A17, A18, A27, and A28) and heavy tower crane structures, and crane
accidents due to bad weather (A5). The results of the risk agent potential are
in line with previous research that there are 6 factors that cause many crane
accidents and 3 of them are due to weather and external factors, due to human
or worker error, and due to method or technical errors in work, especially in
lifting activities (Radlov & Ivanov, 2020).
risk agentThe first
potential is due to fatigue, namely A2, A10 and A22. This risk agent has a big
possibility in every activity, where loss of concentration due to fatigue can
be influenced by work shifts where before 5 am there are changes in cortisol,
body temperature and melatonin levels which affect worker performance. This
results in working at night, cortisol levels are higher in the afternoon
(before work) than in the morning (after work). This difference in cortisol
levels will affect work fatigue (Ihsan & Salami, 2012). Fatigue
priority risk agent has continuity with other risk agents, namely workers who
do not pay attention to posture or ergonomics (A17). This can occur in manual
lifting work, namely crane mate lifting work, where working ergonomically can
affect fatigue levels where the most important factor affecting blood pressure
systolic and heart rate are risks related to ergonomics or posture at work, so
the greater the risk of ergonomics, the more prone to fatigue (Muharmi & Ariesyady, 2012). The
determining factor for body temperature is ambient temperature, so that the
risk agent also has continuity with the priority risk agent for bad weather in
this case which can be temperature, climate and wind speed and direction (A5,
A13, and A25).
House of risk Phase II
In the
House of Risk Phase II, the priority risk agent results (the highest 80%) will
carry out risk mitigation designs in order to reduce the possibility of these
risks occurring. This stage focuses more on providing preventive action to
priority risk agents and determining the correlation value between preventive
action and risk agents. This correlation assessment is carried out by
brainstorming and interviewing experts related to lifting activities on
platforms. After knowing the correlation value and the possibility of its implementation,
the effectiveness of the recommended preventive action will be calculated, then
the effectiveness of the difficulty of the preventive action will be calculated
and the ETD values will be ranked.
Figure 2. Preventive
Action
Based on
discussions and interviews with existing priority risk agents, 48 mitigation
actions are suggested, out of the 48 suggested mitigation actions there is 1
preventive action that has a difficulty value of 5, there are 10 preventive actions
that have a difficulty value of 4, and 37 preventive actions that have a value
of 3. Making improvements by implementing preventive action certainly takes
time in stages. This is based on several factors including the required
resources, costs or costs required, and the time of application. Therefore, the
preventive measures that have been prepared previously will prioritize
preventive measures with the smallest probability value, namely 3, which means
that the preventive measures are easy to implement.
Peptical action that can be
implemented in general include re-education regarding safety carried out
periodically by the HSE, providing PPE, checking the completeness of PPE every
day before workers enter the work area, providing education regarding ergonomics
principles to all workers by the HSE, providing symbols/ reminder banners
regarding ergonomics rules, checking worker certification,
implementing/carrying out a health check system for all workers before doing
work, holding toolbox meetings before work is done, checking/inspecting slings
periodically, monitoring workers' working hours and rest hours, use a
monitoring system by the Safety Man in the field, determine the maximum
speed/angle of crane maneuvers on the platform in the lifting plan, limiting
the area and steering route, making innovations/modifications to add cameras or
parking alarms, using a type of crane whose boom parts/position can be adjusted
(lengthened/ shortened).
HIRADC
HIRADC
(Hazard Identification Risk Assessment and Determining Control) in this study
uses the results of priority risk agents (80% highest) where the data is the
result of the House of risk Phase I method. The HOR I data will be designed for
risk mitigation in accordance with the House method of risk Phase II. By using
data from the HOR phase I and HOR phase II methods, it is hoped that the HIRADC
method can see a reduction in potential risk.
Figure 3. Graph of Decrease in Potential Risk Value
Based on
the HIRADC method, potential risk agents are generated which are categorized
into 2 levels of risk, namely extreme risk and high risk. Of the 16 potential
risk agents, there are 3 risk agents in the extreme risk category and 13 in the
high risk category. After being given preventive action there is a decrease in
the level of risk, where there are 3 categories of moderate risk and 13
categories of low risk.
The impact of OSH risk management on work
productivity and quality of construction projects
K3 (Health, Safety and Security)
risk management in construction projects has a broad impact on work
productivity and project quality. The following is a more detailed description
of these impacts:
Increased Work Productivity
Effective implementation of OHS risk management creates
a safe and healthy work environment. Workers who feel secure tend to focus and
concentrate more on their work, reduce distractions, and increase productivity.
Reducing the potential risk of injury or accident means workers can work
without the worry and worry of unexpected interruptions (Noviana et al., 2023).
Reduction of Downtime and Interruptions
Good K3 risk management helps reduce the frequency of
work accidents or incidents. This leads to a reduction in downtime resulting
from accidents or necessary repairs. Reduced downtime means projects can
continue running without being hampered by preventable safety issues (Toyib, 2022).
Project Quality Improvement
Focusing on K3 can prevent injuries or damage that can
damage the quality of work. Workers who work in a safe and orderly environment
tend to produce better and better quality work. Avoiding defects or damage in
the early stages of a project can reduce the need for later repairs, thereby
improving the overall quality of the project (Sholihah, 2018).
Cost and Time Savings
The adverse impact of accidents or work incidents can
cause project delays and additional costs for repairs. Effective OHS risk
management can avoid the additional costs and time usually required to address
the negative consequences of accidents or incidents (Irawan, 2023).
Positive Image and Reputation
Companies that implement strong OHS risk management
demonstrate a commitment to worker welfare and a safe work environment. This
positive image helps in building a good reputation among workers, clients, and
the general public, which can ultimately help in getting new projects and
maintaining good business relationships (Chaerudin et al., 2020).
Regulatory Compliance
Good OHS risk management ensures that the company
complies with all regulations and rules related to work safety. This compliance
can prevent legal sanctions and fines that may arise as a result of violations
of K3 regulations. Effective K3 risk management has a significant positive
impact on higher work productivity, reduced risk of downtime and disruption,
increased project quality, cost and time savings, better company image, and
better regulatory compliance (Hasibuan et al., 2023).
Application of Technology and Innovation
in OHS Risk Management
Implementation of Occupational
Safety and Health (K3) risk management has a significant impact on work
productivity and project quality in the context of the construction of the
Semarang - Batang Section of the Natural Gas Transmission Pipeline. With effective
K3 risk management, work accidents and worker health risks can be minimized,
paving the way for a sustainable increase in work productivity. Workers who
work in safe environmental conditions and free from risk of injury can focus on
their tasks without limitations. This contributes to increased worker
efficiency and productivity, which can ultimately accelerate project progress (Mindhayani & Purnomo, 2016).
Not only that, implementing good K3
risk management also has a positive impact on overall project quality. Workers
who are in optimal health conditions and equipped with adequate knowledge and
skills will tend to carry out work more carefully and thoroughly (Khairina et al., 2020). The risk of
defects or failures in the construction process of natural gas transmission
pipelines can be reduced, so that the end result of the project has better
quality. Repairs and modifications due to errors can be reduced, resulting in
projects that are more reliable and comply with established standards (Martaningtyas & Ariesyady, 2018).
In addition, the implementation of
OSH risk management also has positive implications for the reputation of the
project and the company as a whole. Interested parties such as the government,
community and other related parties will see this project as an example of the
company's commitment to maintaining the safety and health of workers, as well
as implementing ethical construction practices. This good reputation can open
doors for wider business opportunities and strengthen cooperative relationships
in the future. Thus, the positive impact of K3 risk management is not only
limited to work productivity and project quality, but also forms a positive
image of the company in the construction industry as a whole.
CONCLUSION
The biggest risk that can arise in
the natural gas transmission pipeline construction project area is during
lifting operations in the natural gas reception area (ORF). The risk events
found consisted of 3 risk events in mobilization activities, 5 in crane
placement activities and 7 in material lifting. There are 36 risk factors (risk
factors) of all activities namely. 9 in mobilization activities, 11 in crane
placement activities and 14 in material lifting activities. Of
the 16 existing risk factors, 48 preventive actions were obtained, but with
limited resources, we prioritized preventive action with the lowest possible
value, namely 3. The HOR method that has been carried out has 3 of the 16
possible risk factors in the extreme risk category and 13 in the high risk
category. After taking preventive measures, the risk level decreased to 3
categories of moderate risk and 13 categories of low risk.
REFERENCES
Adomaitis, N. (2017). South Korea:
Six killed in crane accident during construction of oil platform at shipyard. Business
& Human Rights Resources Center.
Basuki, A. (2023). Interview with
HSE Inspector.
Chaerudin, A., Rani, I. H., &
Alicia, V. (2020). Sumber daya manusia: pilar utama kegiatan operasional
organisasi. CV Jejak (Jejak Publisher).
Chauhan, S., & Siddiqui, D. N. A.
(2018). Hazards Identification & Risk Assessment In Construction Industry. International
Journal of Creative Research Thoughts (IJCRT).
Cheng, M. (2023). 62-year-old
worker killed at Kwai Tsing Container Terminal in suspected crane accident.
https://hongkongfp.com/2023/05/05/62-year-old-worker-killed-at-kwai-tsing-container-terminal-in-suspected-crane-accident/
Dan, L. I. K. L. L., & Jalan, A.
(2021). Komite Nasional Keselamatan Transportasi Republik Indonesia.
Dutch Safety Board. (2016). Summary
Lifting Accident Alphen aan den Rijn.
Fauzy, A. (2019). Metode Sampling.
Universitas Terbuka.
Handayani, P. (2020). Accident And
Incident Analysis.
Hasibuan, P. M., Wirdayani, A.,
Hasibuan, D. F., Nurhasanah, S. A., Adisti, P., Mutia, S., & Utami, T. N.
(2023). Tantangan Penerapan Kesehatan dan Keselamatan Kerja (K3) pada
Perusahaan Multinasional di Indonesia. IJM: Indonesian Journal of
Multidisciplinary, 1(2), 643–653.
Houghton, B. (2022). A Man Dangled
From A Toronto Construction Site Crane & There’s A Terrifying Video.
narcity.com/toronto/a-man-dangled-from-a-toronto-construction-site-crane-theres-a-terrifying-video
Ihsan, T., & Salami, I. R. S.
(2012). Hubungan antara shift kerja dengan tingkatan kelelahan kerja pada
pekerja di pabrik perakitan mobil Indonesia. FTSL ITB, 1–4.
International Organization for
Standardization. (2018). ISO 31000 Risk Management. https://www.iso.org/iso-31000-risk-management.html
Irawan, D. W. P. (2023). Manajemen
Resiko Lingkungan: buku ajar bahan pengajaran mata kuliah Manajemen Resiko
Lingkungan tahun akademik 2022/2023. Prodi Sanitasi Program D III Kampus
Magetan.
Iskandar, L. S. (2022). Manajemen
Resiko& Identifikasi Bahaya Penilaian & Pengendalian Risiko K3.
Khairina, I., Malini, H., &
Huriani, E. (2020). Pengetahuan dan keterampilan perawat dalam pengambilan
keputusan klinis triase. Link, 16(1), 1–5.
Kurniawan, D., & Rudi, R. (2019).
Analisis Faktor Penyebab Keterlambatan Proyek Bangunan Gedung Pemerintah di
Kota Bukittinggi. Rang Teknik Journal, 2(1).
Martaningtyas, M., & Ariesyady,
H. D. (2018). Identifikasi Bahaya Dan Analisis Risiko Pada Jaringan Pipa
Transmisi Crude Oil Di Perusahaan Migas. Jurnal Teknik Lingkungan, 24(2),
1–14.
Mindhayani, I., & Purnomo, H.
(2016). Perbaikan sistem kerja untuk meningkatkan produktivitas karyawan. Penelitian
Dan Aplikasi Sistem Dan Teknik Industri, 10(1), 182841.
Muharmi, I., & Ariesyady, H. D.
(2012). Penilaian Ergonomi terhadap Beban dan Posisi Kerja Manual Material
Handling di Departemen Maintenance Support Service (Studi Kasus: PT. Chevron
Pacific Indonesia). Institut Teknologi Bandung.
Muntoha, A. (2019). Integrasi
Metode House of Risk (HOR), PESTLE, CIMOSA Dalam Implementasi Risk Assessment
Proyek Pembangunan PLTGU Jawa-Bali I. Institut Teknologi Sepuluh Nopember.
Ninu, H. (2022). Nindya Karya
Komitmen Selesaikan Peristiwa Kecelakaan Rafter Crane di Manggarai Barat.
https://flores.tribunnews.com/2022/10/17/nindya-karya-komitmen-selesaikan-peristiwa-kecelakaan-rafter-crane-di-manggarai-barat.
Noviana, A., Taufiq, M., Chafid, N.,
Sarie, F., Saksono, H., & Sumaningrum, N. D. (2023). Manajemen K3.
Cendikia Mulia Mandiri.
Nyoman Pujawan, I., & Geraldin,
L. H. (2009). House of risk: a model for proactive supply chain risk
management. Business Process Management Journal, 15(6), 953–967.
OSHA. (2012). Inspection:
504678.015 - Spancrete.
OSHA. (2018). Inspection:
1203163.015 - Veritas Steel Llc.
OSHA. (2021). US Department of
Labor investigation of crane collapse, double fatality on Interstate 10 finds
Lufkin company failed to assemble crane properly.
Parveen, H., & Showkat, N.
(2017). Non-Probability and Probability Sampling. Communications Research.
Pratama, M. F. R. (2021). Analisa
Manajemen Risiko Keselamatan Dan Kesehatan Kerja (K3) Pada Proyek Konstruksi.
Universitas Hasanuddin.
Radlov, K., & Ivanov, G. (2020).
Analysis of accidents with tower cranes on construction sites and
recommendations for their prevention. IOP Conference Series: Materials
Science and Engineering, 951(1), 12025.
Sadidi, J., Gholamnia, R., Gharabagh,
M. J., & Mosavianasl, Z. (2016). Evaluation of Safety Indexes of the
Tower Crane with the FMEA Model (A Case Study: Tower Cranes Mounted in the City
of Mashhad in 2016).
Sholihah, Q. (2018). Keselamatan
dan Kesehatan Kerja Konstruksi. Universitas Brawijaya Press.
Strohmandl, J., Tomek, M., Vargová,
S., & Čujan, Z. (2019). The use of the FMEA method for the evaluation of
failures in crawler cranes. MATEC Web of Conferences, 263, 1004.
Toyib, M. A. (2022). Analisis
Risiko Kerja Pada Departemen Produksi Pipa Menggunakan Metode Hazard
Identification Risk Assesment And Risk Control (Studi kasus: PT. XYZ).
Universitas Islam Sultan Agung.
Umah, A. (2021). Duh, Suplai &
Pasar Gas di Jateng Melimpah, Tapi Gak Ada Pipa.
https://www.cnbcindonesia.com/news/20210416181212-4-238558/duh-suplai-pasar-gas-di-jateng-melimpah-tapi-gak-ada-pipa
Zulfahmi, d. L. R. (2022). Akibat Rem Blong, Truk
Crane Tabrak Tiang Listrik dan Rusak Rumah Makan.
https://www.tvonenews.com/daerah/sumatera/59816-akibat-rem-blong-truk-crane-tabrak-tiang-listrik-dan-rusak-rumah-makan
Copyright holders:
Gayatri Nuansa Putri, Herto Dwi
Ariesyadi (2023)
First publication right:
Devotion - Journal of Research and Community
Service
This
article is licensed under a Creative
Commons Attribution-ShareAlike 4.0 International